Public beta. Not yet independently reviewed. ProjectWhitehall republishes public records from official sources. It is not an investigation, a legal finding or advice. Registers can be late, incomplete or wrong, and a link between records does not show wrongdoing. Absence of a record does not mean absence of activity. Always check the original source, which we link on every entry. We have already made mistakes and list them all in the corrections log.

ProjectWhitehall

Ofgem compliance and enforcement cases, page 16 of 17

Cases 226 to 240 of 252, newest first, each in Ofgem's words. What this list is and is not, and how it was read, are on the first page of the list.

The status and every other word is Ofgem's, as it stood when we retrieved it. An open case is not a finding. We add no label to a case or a company, and no case is linked to a licence holder, a company page, a donation or a contract.

Cases 226 to 240 of 252. Page 16 of 17. Every row is on one of these pages.

3 Nov 2011: Investigation into British Gas' compliance with obligations under SLC 27.8 with respect to treatment of customers in payment difficulty

Type as published: Enforcement case. Published 3 Nov 2011. Closed 1 Nov 2011. Status as published: Closed.

Decision (as Ofgem words it): Decision to close the Investigation into British Gas' compliance with obligations under SLC 27.8 with respect to treatment of customers in payment difficulty

Ofgem has confirmed its decision to close its investigation into British Gas' compliance with obligations under SLC 27.8 with respect to treatment of customers in payment difficulty.

Ofgem’s investigation looked into whether British Gas Trading Limited (British Gas) may have breached standard licence condition 27.8 of its gas and electricity supply licences which requires suppliers to take all reasonable steps to ascertain a domestic customer’s individual ability to pay and requires them to take this into account when calculating instalments.

The case focused on British Gas’ treatment of individual customers. Since the investigation began, British Gas made important changes to its approach and confirmed its acceptance:

a) of the core principle of taking all reasonable steps to establish each individual customer’s ability to pay and to take this into account when agreeing instalments:

(i) in all of its interactions with that customer where it is relevant; and

(ii) at all stages of the debt path, up to and including warrant stage and where customers are seeking reconnection; and

b) of the importance of suppliers building and maintaining a full picture of customer circumstances, over time, and refreshing and taking account of such information as circumstances change, and maintaining records of these.

On the basis of the changes in British Gas’s approach, the apparent historic nature of the problems initially examined, and our ongoing monitoring work in this area Ofgem decided to close the case on administrative priority grounds.

Additionally, Ofgem wrote to suppliers to draw their attention to this decision (see link below). Ofgem will continue to monitor all suppliers’ compliance with their licence obligations around debt management and disconnection.

Further details can be found in the decision document.

The case on Ofgem's site

3 Nov 2011: Investigation into British Gas' compliance with reporting requirements under the Renewables Obligation

Type as published: Enforcement case. Published 3 Nov 2011. Closed 3 Nov 2011. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty on British Gas following our investigation into its compliance with reporting requirements under the Renewables Obligation

The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on British Gas (BG) for its failure to report accurate supply data as required under the Renewables Obligation for England & Wales and Scotland.

By 1 July each year, electricity suppliers are required to inform the Authority of the amount of electricity supplied to customers in England & Wales and Scotland during the previous obligation period (financial year).

Ofgem’s investigation concerned BG’s reporting of electricity supply data from the first obligation period in 2002-03 to the seventh obligation period in 2008-09.

The Authority found that:

• BG misreported the amount of electricity supplied to customers in England & Wales and Scotland each year from the first obligation period in 2002-03 to the seventh obligation period in 2008-09.

• The misreporting amounted to 0.62% of electricity supplied per year on average; and as a result of the misreporting other market participants suffered an aggregate loss of £2.8m over the 7-year period.

BG took appropriate action to address any market impact caused by the error.

The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £1 million on BG.

Further details can be found in the final penalty notice.

The case on Ofgem's site

3 Nov 2011: Notice of decision to impose a financial penalty on British Gas following our investigation into its compliance with reporting requirements under the Renewables Obligation

Type as published: Enforcement case. Published 3 Nov 2011.

Decision for (as Ofgem words it): Investigation into British Gas' compliance with reporting requirements under the Renewables Obligation

The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on British Gas (BG) for its failure to report accurate supply data as required under the Renewables Obligation for England & Wales and Scotland.

By 1 July each year, electricity suppliers are required to inform the Authority of the amount of electricity supplied to customers in England & Wales and Scotland during the previous obligation period (financial year).

Ofgem’s investigation concerned BG’s reporting of electricity supply data from the first obligation period in 2002-03 to the seventh obligation period in 2008-09.

The Authority found that:

• BG misreported the amount of electricity supplied to customers in England & Wales and Scotland each year from the first obligation period in 2002-03 to the seventh obligation period in 2008-09.

• The misreporting amounted to 0.62% of electricity supplied per year on average; and as a result of the misreporting other market participants suffered an aggregate loss of £2.8m over the 7-year period.

BG took appropriate action to address any market impact caused by the error.

The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £1 million on BG.

Further details can be found in the final penalty notice.

The case on Ofgem's site

16 Aug 2011: Decision to close the investigation into EDF Energy plc’s compliance with the Consumer Protection from Unfair Trading Regulations 2008 (CPRs) with respect to regulations prohibiting commercial practices which amount to misleading omissions

Type as published: Enforcement case. Published 16 Aug 2011.

Decision for (as Ofgem words it): Investigation into EDF Energy plc’s compliance with the Consumer Protection from Unfair Trading Regulations 2008 (CPRs) with respect to regulations prohibiting commercial practices which amount to misleading omissions

Ofgem investigated whether EDF Energy plc (EDF) might have breached Regulation 3(4) read together with Regulation 6(1) of the CPRs.

These regulations prohibit commercial practices which amount to misleading omissions, in other words, which omit or hide material information and as a result cause, or would likely cause, the average consumer to take a transactional decision he would not otherwise have taken.

Ofgem was concerned that consumers may have taken decisions to use the IVR system but without EDF having informed them of the financial consequences of doing so, especially when compared to them providing meter readings directly to EDF’s customer service operators.

Ofgem decided to close the investigation, on the basis that:

• EDF rectified the problem in April 2010 and took steps to ensure it will not arise again;

• EDF agreed to compensate consumers who suffered loss with a compensation package which appeared reasonable;

• Ofgem’s enforcement powers in respect of breaches of the CPRs extend to seeking a court order or formal undertakings that the conduct giving rise to the breach will not happen again, and EDF took steps of its own volition to ensure the problem would not happen again

Further details can be found in the decision document.

Following closure of this investigation, Ofgem wrote to all domestic suppliers on 16 August 2011 indicating that we consider it essential that any system which is used to assess customers’ bills must operate in a way that ensures customers are billed as accurately and fairly as possible, and that consumers understand and have confidence in the process. You can read this letter by following the link below.

Noting that Energy UK operates the "Code of Practice for Accurate Bills" ("the code") which requires that the suppliers which are party to it use all available information to produce accurate, clear and timely bills, Ofgem wrote to Energy UK to draw its attention to the issue so that they might consider whether suppliers are acting in compliance with the code.

The case on Ofgem's site

16 Aug 2011: Investigation into EDF Energy plc’s compliance with the Consumer Protection from Unfair Trading Regulations 2008 (CPRs) with respect to regulations prohibiting commercial practices which amount to misleading omissions

Type as published: Enforcement case. Published 16 Aug 2011. Closed 16 Aug 2011. Status as published: Closed.

Decision (as Ofgem words it): Decision to close the investigation into EDF Energy plc’s compliance with the Consumer Protection from Unfair Trading Regulations 2008 (CPRs) with respect to regulations prohibiting commercial practices which amount to misleading omissions

Ofgem investigated whether EDF Energy plc (EDF) might have breached Regulation 3(4) read together with Regulation 6(1) of the CPRs.

These regulations prohibit commercial practices which amount to misleading omissions, in other words, which omit or hide material information and as a result cause, or would likely cause, the average consumer to take a transactional decision he would not otherwise have taken.

Ofgem was concerned that consumers may have taken decisions to use the IVR system but without EDF having informed them of the financial consequences of doing so, especially when compared to them providing meter readings directly to EDF’s customer service operators.

Ofgem decided to close the investigation, on the basis that:

• EDF rectified the problem in April 2010 and took steps to ensure it will not arise again;

• EDF agreed to compensate consumers who suffered loss with a compensation package which appeared reasonable;

• Ofgem’s enforcement powers in respect of breaches of the CPRs extend to seeking a court order or formal undertakings that the conduct giving rise to the breach will not happen again, and EDF took steps of its own volition to ensure the problem would not happen again

Further details can be found in the decision document.

Following closure of this investigation, Ofgem wrote to all domestic suppliers on 16 August 2011 indicating that we consider it essential that any system which is used to assess customers’ bills must operate in a way that ensures customers are billed as accurately and fairly as possible, and that consumers understand and have confidence in the process. You can read this letter by following the link below.

Noting that Energy UK operates the "Code of Practice for Accurate Bills" ("the code") which requires that the suppliers which are party to it use all available information to produce accurate, clear and timely bills, Ofgem wrote to Energy UK to draw its attention to the issue so that they might consider whether suppliers are acting in compliance with the code.

The case on Ofgem's site

16 May 2011: Investigation into National Grid Gas plc’s compliance with Special Conditions E2B, E6 and E20, Standard Special Condition D9 and A40 of its gas transporter licence in respect of its Distribution Networks

Type as published: Enforcement case. Published 16 May 2011. Closed 13 May 2011. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty on National Grid Gas plc following our investigation into its compliance with Special Conditions E2B, E6 and E20, Standard Special Condition D9 and A40 of its gas transporter licence

The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on National Grid Gas plc (NGG) for its failure to comply with Special Conditions E2B, E6 and E20, Standard Special Condition D9 and A40 of its gas transporter licence with respect to the reporting of its mains decommissioning activities.

Under those provisions of its licence, NGG was required to provide to Ofgem for each regulatory year a report of the mains decommissioning work completed by NGG in that year.

The ability of regulators to rely on accurate information from regulated companies is a fundamental part of the regulatory regime. The Authority therefore regards any contraventions of the obligations on regulatory information as serious.

Ofgem conducted and completed an extensive investigation into NGG’s regulatory reporting in this context for the years 2005/06, 2006/07 and 2007/08.

The Authority found that NGG contravened the provisions of Special Conditions E2B, E6 and E20 and Standard Special Conditions D9 and A40 of its licence during the relevant period.

The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £8 million on NGG.

Further details can be found in the final penalty notice.

The case on Ofgem's site

16 May 2011: Notice of decision to impose a financial penalty on National Grid Gas plc following our investigation into its compliance with Special Conditions E2B, E6 and E20, Standard Special Condition D9 and A40 of its gas transporter licence

Type as published: Enforcement case. Published 16 May 2011.

Decision for (as Ofgem words it): Investigation into National Grid Gas plc’s compliance with Special Conditions E2B, E6 and E20, Standard Special Condition D9 and A40 of its gas transporter licence in respect of its Distribution Networks

The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on National Grid Gas plc (NGG) for its failure to comply with Special Conditions E2B, E6 and E20, Standard Special Condition D9 and A40 of its gas transporter licence with respect to the reporting of its mains decommissioning activities.

Under those provisions of its licence, NGG was required to provide to Ofgem for each regulatory year a report of the mains decommissioning work completed by NGG in that year.

The ability of regulators to rely on accurate information from regulated companies is a fundamental part of the regulatory regime. The Authority therefore regards any contraventions of the obligations on regulatory information as serious.

Ofgem conducted and completed an extensive investigation into NGG’s regulatory reporting in this context for the years 2005/06, 2006/07 and 2007/08.

The Authority found that NGG contravened the provisions of Special Conditions E2B, E6 and E20 and Standard Special Conditions D9 and A40 of its licence during the relevant period.

The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £8 million on NGG.

Further details can be found in the final penalty notice.

The case on Ofgem's site

28 Apr 2011: Investigation into First Utility’s compliance with SLC 27 with respect to disconnections and customers in payment difficulty – Provisional Order

Type as published: Enforcement case. Published 28 Apr 2011. Closed 28 Apr 2011. Status as published: Closed.

Decision (as Ofgem words it): Notice of non-confirmation of a Provisional Order - Investigation into First Utility’s compliance with SLC 27 with respect to disconnections and customers in payment difficulty

Ofgem investigated First Utility in relation to concerns that it was not complying with Standard Licence Condition 27 of its gas and electricity supply licenses.

A provisional order was made against First Utility Limited on 22 December 2010 requiring the company to comply with SLC 27 with respect to its treatment of customers in payment difficulty.

Further details can be found in the Provisional Order document.

Following a review of evidence obtained from First Utility, Ofgem was satisfied that the company had met the terms of the provisional order within the required deadlines.

Ofgem issued a notice of non-confirmation on 28 April 2011.

The case on Ofgem's site

28 Apr 2011: Notice of non-confirmation of a Provisional Order - Investigation into First Utility’s compliance with SLC 27 with respect to disconnections and customers in payment difficulty

Type as published: Enforcement case. Published 28 Apr 2011.

Decision for (as Ofgem words it): Investigation into First Utility’s compliance with SLC 27 with respect to disconnections and customers in payment difficulty – Provisional Order

Ofgem investigated First Utility in relation to concerns that it was not complying with Standard Licence Condition 27 of its gas and electricity supply licenses.

A provisional order was made against First Utility Limited on 22 December 2010 requiring the company to comply with SLC 27 with respect to its treatment of customers in payment difficulty.

Further details can be found in the Provisional Order document.

Following a review of evidence obtained from First Utility, Ofgem was satisfied that the company had met the terms of the provisional order within the required deadlines.

Ofgem issued a notice of non-confirmation on 28 April 2011.

The case on Ofgem's site

13 Apr 2011: Investigation into Central Networks East plc’s and Central Networks West plc's compliance with SLC 4D, SLC 12 and SLC 30 of the electricity distribution licence

Type as published: Enforcement case. Published 13 Apr 2011. Closed 13 Apr 2011. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty on Central Networks East plc and Central Networks West plc following our investigation into its compliance with SLC 4D, SLC 12 and SLC 30 of the electricity distribution licence

The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on Central Networks East plc and Central Networks West plc (Central Networks) for its failure to comply with obligations under its electricity distribution licence, specifically standard licence condition 4D ("SLC 4D"), standard licence condition 12 ("SLC 12") and standard licence condition 30 ("SLC 30").

The obligation on licensees in SLC 4D and SLC 12 is to provide offers for connection as soon as practicable/reasonably practicable and in any event within three months of receipt of an application which contains all such information as the licensee may reasonably require for the purposes of formulating the offer. SLC 30 requires a licensee to have available to itself such "resources, including management and financial resources…as will enable it to…comply in all respects with its obligations under this licence".

Ofgem’s investigation concerned applications and offers for connection made between 1 July 2004 and 11 October 20102, and the monitoring systems that were in place at the time to ensure compliance with the obligations regarding connection offers.

The Authority found that:

Central Networks did not have monitoring systems in place sufficient to enable it effectively to monitor compliance with its obligations under the electricity distribution licence between 1 July 2004 and the time of the introduction of a new system for connections in January 2009, in breach of SLC 30;

There have been 14 instances where Central Networks has breached the three-month timeframe required in SLC 12 when the time of the contravention took place on or after 9 December 20083; and

There has been one case where Central Networks has breached the three-month timeframe required in SLC 12, and two cases where Central Networks has breached the requirement set out in SLC 4D, when the time of the contravention took place before 9 December 2008.

The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £400,000 on Central Networks.

Further details can be found in the final penalty notice.

The case on Ofgem's site

13 Apr 2011: Investigation into Electricity North West Ltd's compliance with SLC 4D and SLC 12 of its electricity distribution licence with respect to offers for connection

Type as published: Enforcement case. Published 13 Apr 2011. Closed 13 Apr 2011. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty on Electricity North West Ltd following our investigation into its compliance with SLC 4D and SLC 12 of its electricity distribution licence with respect to offers for connection

The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on Electricity North West (ENW) for its failure to comply with standard licence condition 4D and standard licence condition 12 of its electricity distribution licence with respect to offers for connection.

Under SLC 4D (Requirement to Offer Terms for Use of System and Connection), ENW was obliged to provide offers for connection as soon as practicable, and in any event within three months of receipt of an application which contained all such information as ENW may have reasonably required for the purpose of formulating the terms of the offer.

Since 1 June 2008 the obligations in SLC 4D have been set out in SLC 12 (Requirement to Offer Terms for Use of System and Connection). SLC 12 requires ENW to provide offers for connection as soon as reasonably practicable, and in any event within three months of receipt of an application which contains all such information as ENW may reasonably require for the purpose of formulating the terms of the offer.

Ofgem’s investigation concerned applications and offers for connections made from 1 April 2007. During this time, ENW has accepted that there were 22 breaches of SLC 4D and six breaches of SLC 12. The Authority is satisfied that ENW contravened SLC 4D and SLC 12.

The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £100,000 on ENW.

Further details can be found in the final penalty notice.

The case on Ofgem's site

13 Apr 2011: Investigation into Scottish Hydro Electric Power Distribution's compliance with SLC 4D, SLC 12 and SLC 30 of its electricity distribution licence

Type as published: Enforcement case. Published 13 Apr 2011. Closed 13 Apr 2011. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty on Scottish Hydro Electric Power Distribution following our investigation into its compliance with SLC 4D, SLC 12 and SLC 30 of its electricity distribution licence

The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on Scottish Hydro Electric Power Distribution (SHEPD) for its failure to comply with its licence obligations under its electricity distribution licence, specifically standard licence condition 4D, standard licence condition 12 and standard licence condition 30.

The obligation on licensees in SLC 4D and SLC 12 is to provide offers for connection as soon as practicable/reasonably practicable and in any event within three months of receipt of an application which contains all such information as the licensee may reasonably require for the purposes of formulating the offer. SLC 30 requires a licensee to have available to itself such "resources, including management and financial resources as will enable it to comply in all respects with its obligations under this licence".

Our investigation concerned applications and offers for connection made from 1 July 2004 to 15 July 2009, and the monitoring systems that were in place to ensure compliance with the obligations regarding connection offers. During this period SHEPD received 48,593 enquiries regarding connection applications.

The Authority found that:

SHEPD did not have appropriate monitoring systems in place to enable it to comply with its obligations under the electricity distribution licence, in breach of SLC 30;

There have been 18 cases where SHEPD has breached the three month timeframe required in SLC 12; and

There have been six cases where SHEPD has breached the three month timeframe required in SLC 4D.

The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £500,000 on SHEPD.

Further details can be found in the final penalty notice.

The case on Ofgem's site

13 Apr 2011: Notice of decision to impose a financial penalty on Central Networks East plc and Central Networks West plc following our investigation into its compliance with SLC 4D, SLC 12 and SLC 30 of the electricity distribution licence

Type as published: Enforcement case. Published 13 Apr 2011.

Decision for (as Ofgem words it): Investigation into Central Networks East plc’s and Central Networks West plc's compliance with SLC 4D, SLC 12 and SLC 30 of the electricity distribution licence

The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on Central Networks East plc and Central Networks West plc (Central Networks) for its failure to comply with obligations under its electricity distribution licence, specifically standard licence condition 4D ("SLC 4D"), standard licence condition 12 ("SLC 12") and standard licence condition 30 ("SLC 30").

The obligation on licensees in SLC 4D and SLC 12 is to provide offers for connection as soon as practicable/reasonably practicable and in any event within three months of receipt of an application which contains all such information as the licensee may reasonably require for the purposes of formulating the offer. SLC 30 requires a licensee to have available to itself such "resources, including management and financial resources…as will enable it to…comply in all respects with its obligations under this licence".

Ofgem’s investigation concerned applications and offers for connection made between 1 July 2004 and 11 October 20102, and the monitoring systems that were in place at the time to ensure compliance with the obligations regarding connection offers.

The Authority found that:

Central Networks did not have monitoring systems in place sufficient to enable it effectively to monitor compliance with its obligations under the electricity distribution licence between 1 July 2004 and the time of the introduction of a new system for connections in January 2009, in breach of SLC 30;

There have been 14 instances where Central Networks has breached the three-month timeframe required in SLC 12 when the time of the contravention took place on or after 9 December 20083; and

There has been one case where Central Networks has breached the three-month timeframe required in SLC 12, and two cases where Central Networks has breached the requirement set out in SLC 4D, when the time of the contravention took place before 9 December 2008.

The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £400,000 on Central Networks.

Further details can be found in the final penalty notice.

The case on Ofgem's site

13 Apr 2011: Notice of decision to impose a financial penalty on Electricity North West Ltd following our investigation into its compliance with SLC 4D and SLC 12 of its electricity distribution licence with respect to offers for connection

Type as published: Enforcement case. Published 13 Apr 2011.

Decision for (as Ofgem words it): Investigation into Electricity North West Ltd's compliance with SLC 4D and SLC 12 of its electricity distribution licence with respect to offers for connection

The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on Electricity North West (ENW) for its failure to comply with standard licence condition 4D and standard licence condition 12 of its electricity distribution licence with respect to offers for connection.

Under SLC 4D (Requirement to Offer Terms for Use of System and Connection), ENW was obliged to provide offers for connection as soon as practicable, and in any event within three months of receipt of an application which contained all such information as ENW may have reasonably required for the purpose of formulating the terms of the offer.

Since 1 June 2008 the obligations in SLC 4D have been set out in SLC 12 (Requirement to Offer Terms for Use of System and Connection). SLC 12 requires ENW to provide offers for connection as soon as reasonably practicable, and in any event within three months of receipt of an application which contains all such information as ENW may reasonably require for the purpose of formulating the terms of the offer.

Ofgem’s investigation concerned applications and offers for connections made from 1 April 2007. During this time, ENW has accepted that there were 22 breaches of SLC 4D and six breaches of SLC 12. The Authority is satisfied that ENW contravened SLC 4D and SLC 12.

The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £100,000 on ENW.

Further details can be found in the final penalty notice.

The case on Ofgem's site

13 Apr 2011: Notice of decision to impose a financial penalty on Scottish Hydro Electric Power Distribution following our investigation into its compliance with SLC 4D, SLC 12 and SLC 30 of its electricity distribution licence

Type as published: Enforcement case. Published 13 Apr 2011.

Decision for (as Ofgem words it): Investigation into Scottish Hydro Electric Power Distribution's compliance with SLC 4D, SLC 12 and SLC 30 of its electricity distribution licence

The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on Scottish Hydro Electric Power Distribution (SHEPD) for its failure to comply with its licence obligations under its electricity distribution licence, specifically standard licence condition 4D, standard licence condition 12 and standard licence condition 30.

The obligation on licensees in SLC 4D and SLC 12 is to provide offers for connection as soon as practicable/reasonably practicable and in any event within three months of receipt of an application which contains all such information as the licensee may reasonably require for the purposes of formulating the offer. SLC 30 requires a licensee to have available to itself such "resources, including management and financial resources as will enable it to comply in all respects with its obligations under this licence".

Our investigation concerned applications and offers for connection made from 1 July 2004 to 15 July 2009, and the monitoring systems that were in place to ensure compliance with the obligations regarding connection offers. During this period SHEPD received 48,593 enquiries regarding connection applications.

The Authority found that:

SHEPD did not have appropriate monitoring systems in place to enable it to comply with its obligations under the electricity distribution licence, in breach of SLC 30;

There have been 18 cases where SHEPD has breached the three month timeframe required in SLC 12; and

There have been six cases where SHEPD has breached the three month timeframe required in SLC 4D.

The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £500,000 on SHEPD.

Further details can be found in the final penalty notice.

The case on Ofgem's site

Cases 226 to 240 of 252. Page 16 of 17. Every row is on one of these pages.

Contains public sector information licensed under the Open Government Licence v3.0.