Public beta. Not yet independently reviewed. ProjectWhitehall republishes public records from official sources. It is not an investigation, a legal finding or advice. Registers can be late, incomplete or wrong, and a link between records does not show wrongdoing. Absence of a record does not mean absence of activity. Always check the original source, which we link on every entry. We have already made mistakes and list them all in the corrections log.

ProjectWhitehall

Ofgem compliance and enforcement cases, page 13 of 17

Cases 181 to 195 of 252, newest first, each in Ofgem's words. What this list is and is not, and how it was read, are on the first page of the list.

The status and every other word is Ofgem's, as it stood when we retrieved it. An open case is not a finding. We add no label to a case or a company, and no case is linked to a licence holder, a company page, a donation or a contract.

Cases 181 to 195 of 252. Page 13 of 17. Every row is on one of these pages.

5 Mar 2015: Investigation into ScottishPower's compliance with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

Type as published: Enforcement case. Published 5 Mar 2015. Closed 5 Mar 2015. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty following an investigation into compliance by ScottishPower with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

The Authority has decided to impose a financial penalty on ScottishPower following an investigation into the company’s compliance with its obligations under Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009.

The Community Energy Saving Programme ("CESP") was a policy, set down in legislation, designed to improve domestic energy efficiency standards in the most deprived geographical areas across Great Britain. The relevant legislation was the Electricity and Gas (Community Energy Saving Programme) Order 2009 ("CESP Order"). Under Article 14(1) of the CESP Order, generators and suppliers had to achieve their carbon emissions reduction obligation by promoting qualifying actions to domestic energy users in low income areas.

The Authority found that ScottishPower breached Article 14(1) of the CESP Order having failed to achieve its carbon emissions reduction obligations by promoting qualifying actions to domestic energy users by 31 December 2012. ScottishPower as a whole delivered 69.96% of its obligation and had a shortfall of 554,373 tCO2.

The particular ScottishPower licensees which failed to meet their obligations were ScottishPower Energy Retail Limited and ScottishPower Generation Limited.

The Authority noted that ScottishPower undertook mitigation activity by April 2013 to mitigate its carbon saving shortfall in full. ScottishPower also over-delivered which resulted in additional households receiving measures. The Authority had regard to this in setting the final level of penalty.

A payment of £2.4 million (less a nominal £1 penalty on each of the ScottishPower licensees) will be made by ScottishPower to the ScottishPower Energy People Trust which will fund projects with the aim of pursuing the following objectives:

• promotion of carbon emissions reduction in domestic homes;

• the promotion of energy efficiency in domestic homes; or

• fuel poverty.

A financial penalty of £1 by each of the ScottishPower licensees is to be made by 17 April 2015.

The case on Ofgem's site

5 Mar 2015: Investigation into SSE and its compliance with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

Type as published: Enforcement case. Published 5 Mar 2015. Closed 5 Mar 2015. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty on SSE following an investigation into its compliance with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

The Authority has decided to impose a financial penalty on SSE following an investigation into the company’s compliance with its obligations under Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009.

The Community Energy Saving Programme ("CESP") was a policy, set down in legislation, designed to improve domestic energy efficiency standards in the most deprived geographical areas across Great Britain. The relevant legislation was the Electricity and Gas (Community Energy Saving Programme) Order 2009 ("CESP Order"). Under Article 14(1) of the CESP Order, generators and suppliers had to achieve their carbon emissions reduction obligation by promoting qualifying actions to domestic energy users in low income areas.

The Authority found that SSE breached Article 14(1) of the CESP Order having failed to achieve its carbon emissions reduction obligations by promoting qualifying actions to domestic energy users by 31 December 2012. SSE as a whole delivered 90.9% of its obligation and had a shortfall of 252,168 tCO2. SSE’s shortfall as a percentage of its obligation (9.1%) was smaller than any other OP under CESP.

The particular SSE licensees which failed to meet their obligations were SSE Energy Supply Limited, Southern Electric Gas Ltd, SSEPG (Operations) Ltd, Medway Power Ltd, Keadby Generation Ltd, Greater Gabbard Offshore Windfarm Ltd, Uskmouth Power Company Ltd, Clyde Wind Farm (Scotland) Ltd and Griffin Wind Farm Ltd.

The Authority noted that SSE undertook mitigation activity by May 2013 to mitigate its carbon saving shortfall in full. SSE also over-delivered which resulted in 346 more households receiving measures. The Authority had regard to this in setting the final level of penalty.

A payment of £1.75 million (less a nominal £1 penalty on each of the SSE licensees) will be made by SSE to vulnerable consumers, through the Foundations Independent Living Trust, Energy Action Scotland and the Citizen’s Advice Bureau for use in Wales with the aim of pursuing the following objectives:

• promotion of carbon emissions reduction in domestic homes;

• the promotion of energy efficiency in domestic homes; or

• fuel poverty.

A financial penalty of £1 by each of the SSE licensees is to be made by 17 April 2015.

The case on Ofgem's site

5 Mar 2015: Notice of decision to impose a financial penalty following an investigation into compliance by British Gas with Article 9(1) and Article 9(1A) of the Electricity and Gas (Carbon Emissions Reduction) Order 2008 (as amended)

Type as published: Enforcement case. Published 5 Mar 2015.

Decision for (as Ofgem words it): Investigation into British Gas’ compliance with Article 9(1) and Article 9(1A) of the Electricity and Gas (Carbon Emissions Reduction) Order 2008 (as amended)

The Authority has decided to impose a financial penalty on British Gas following an investigation into the company’s compliance with its obligations under Article 9(1) and Article 9(1A) of the Electricity and Gas (Carbon Emissions Reduction) Order 2008 (as amended).

The Carbon Emissions Reduction Target (CERT) was a policy, set down in legislation, designed to improve domestic energy efficiency standards across households in Great Britain. The policy was designed to contribute to the UK’s legally binding emissions reduction commitments. The relevant legislation was the Electricity and Gas (Carbon Emissions Reduction) Order 2008, as amended ("CERT Order"). Article 9(1) of the CERT Order required that certain gas and electricity suppliers must achieve their carbon emissions reduction obligations by promoting qualifying actions to domestic energy users in Great Britain. Article 9(1A) of the CERT Order required those suppliers to achieve a defined proportion of that obligation by promoting insulation measures.

The Authority noted that British Gas initially had an obligation to promote carbon savings equivalent to 96,279.607 ktCO2. Under Article 9(1), as a group, British Gas delivered 98.9% of its overall CERT target and had a shortfall of 1,075.111 ktCO2 at 31 December 2012. Under Article 9(1A), as a group, it delivered 95.5% of its Insulation Obligation target of 24,119.192 ktCO2 and had a shortfall of 1,089.622 ktCO2 at 31 December 2012. The shortfall of British Gas’s overall CERT target was incurred entirely against its Insulation Obligation. British Gas accepts that it breached Articles 9(1) and 9(1A) of the CERT Order.

The Authority noted that British Gas undertook mitigation action equivalent to the volume of its shortfall associated with not achieving the carbon reduction target promptly by February 2013 (for both the overall CERT obligation and IO). British Gas also over-delivered during CERT mitigation. The Authority had regard to this in setting the level of penalty.

A payment of £500,000 (less a nominal £1 penalty) has been made by British Gas to the British Gas Energy Trust ("BGET"). The BGET shall distribute the redress monies to organisations which pursue any or all of the following objectives for vulnerable customers:

• the promotion of energy efficiency in domestic homes;

• the alleviation of fuel poverty;

• the reduction of carbon emissions in domestic homes.

A financial penalty of £1 is to be made by British Gas by 17 April 2015.

The case on Ofgem's site

5 Mar 2015: Notice of decision to impose a financial penalty following an investigation into compliance by GDF SUEZ/IPM with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

Type as published: Enforcement case. Published 5 Mar 2015. Closed 5 Mar 2015.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty following an investigation into compliance by GDF SUEZ/IPM with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

The Authority has decided to impose a financial penalty on GDF SUEZ/IPM following an investigation into the company’s compliance with its obligations under Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009.

The Community Energy Saving Programme ("CESP") was a policy, set down in legislation, designed to improve domestic energy efficiency standards in the most deprived geographical areas across Great Britain. The relevant legislation was the Electricity and Gas (Community Energy Saving Programme) Order 2009 ("CESP Order"). Under Article 14(1) of the CESP Order, generators and suppliers had to achieve their carbon emissions reduction obligation by promoting qualifying actions to domestic energy users in low income areas.

The Authority found that GDF SUEZ/IPM breached Article 14(1) of the CESP Order having failed to achieve its carbon emissions reduction obligations by promoting qualifying actions to domestic energy users by 31 December 2012. GDF SUEZ/IPM as a whole delivered 38.6% of its reduced obligation and had a shortfall of 177,928 tCO2.

The particular GDF SUEZ/IPM licensees which failed to meet their obligations were Saltend Cogeneration Company Limited, Deeside Power Limited and Rugeley Power Generation Limited.

The Authority noted that GDF SUEZ/IPM undertook mitigation activity by March 2013 to mitigate its carbon saving shortfall in full. GDF SUEZ/IPM also delivered mitigation in excess of the level required to address the harm associated with its breach. The Authority had regard to this in setting the final level of penalty.

A payment of £450,000 (less a nominal £2 penalty on GDF SUEZ/IPM licensees) has been made to Age UK with the aim of pursuing the following objectives:

promotion of carbon emissions reduction in domestic homes;

the promotion of energy efficiency in domestic homes; or

fuel poverty.

A financial penalty of £2 is to be made by 17 April 2015.

The case on Ofgem's site

5 Mar 2015: Notice of decision to impose a financial penalty following an investigation into compliance by ScottishPower with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

Type as published: Enforcement case. Published 5 Mar 2015.

Decision for (as Ofgem words it): Investigation into ScottishPower's compliance with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

The Authority has decided to impose a financial penalty on ScottishPower following an investigation into the company’s compliance with its obligations under Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009.

The Community Energy Saving Programme ("CESP") was a policy, set down in legislation, designed to improve domestic energy efficiency standards in the most deprived geographical areas across Great Britain. The relevant legislation was the Electricity and Gas (Community Energy Saving Programme) Order 2009 ("CESP Order"). Under Article 14(1) of the CESP Order, generators and suppliers had to achieve their carbon emissions reduction obligation by promoting qualifying actions to domestic energy users in low income areas.

The Authority found that ScottishPower breached Article 14(1) of the CESP Order having failed to achieve its carbon emissions reduction obligations by promoting qualifying actions to domestic energy users by 31 December 2012. ScottishPower as a whole delivered 69.96% of its obligation and had a shortfall of 554,373 tCO2.

The particular ScottishPower licensees which failed to meet their obligations were ScottishPower Energy Retail Limited and ScottishPower Generation Limited.

The Authority noted that ScottishPower undertook mitigation activity by April 2013 to mitigate its carbon saving shortfall in full. ScottishPower also over-delivered which resulted in additional households receiving measures. The Authority had regard to this in setting the final level of penalty.

A payment of £2.4 million (less a nominal £1 penalty on each of the ScottishPower licensees) will be made by ScottishPower to the ScottishPower Energy People Trust which will fund projects with the aim of pursuing the following objectives:

• promotion of carbon emissions reduction in domestic homes;

• the promotion of energy efficiency in domestic homes; or

• fuel poverty.

A financial penalty of £1 by each of the ScottishPower licensees is to be made by 17 April 2015.

The case on Ofgem's site

5 Mar 2015: Notice of decision to impose a financial penalty on British Gas following our investigation into its compliance with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

Type as published: Enforcement case. Published 5 Mar 2015.

Decision for (as Ofgem words it): Investigation into British Gas’ compliance with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on British Gas for its failure to meet its obligations under Article 14(1) of the Electricity and Gas (Carbon Emissions and Community Energy Saving) Order 2009 ("CESP Order"), and consideration by the Authority of representations or objections received on its proposed penalty. These representations or objections are discussed in the Annex to the Penalty Notice.

The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £1 on British Gas, on the basis that British Gas has made a payment of £10.6 million (less the £1 financial penalty) in consumer redress to the British Gas Energy Trust ("BGET"). The BGET shall distribute the redress monies to organisations which pursue any or all of the following objectives for vulnerable customers:

the promotion of energy efficiency in domestic homes;

the alleviation of fuel poverty;

the reduction of carbon emissions in domestic homes.

Further details can be found in the final Penalty Notice.

The case on Ofgem's site

5 Mar 2015: Notice of decision to impose a financial penalty on SSE following an investigation into its compliance with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

Type as published: Enforcement case. Published 5 Mar 2015.

Decision for (as Ofgem words it): Investigation into SSE and its compliance with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

The Authority has decided to impose a financial penalty on SSE following an investigation into the company’s compliance with its obligations under Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009.

The Community Energy Saving Programme ("CESP") was a policy, set down in legislation, designed to improve domestic energy efficiency standards in the most deprived geographical areas across Great Britain. The relevant legislation was the Electricity and Gas (Community Energy Saving Programme) Order 2009 ("CESP Order"). Under Article 14(1) of the CESP Order, generators and suppliers had to achieve their carbon emissions reduction obligation by promoting qualifying actions to domestic energy users in low income areas.

The Authority found that SSE breached Article 14(1) of the CESP Order having failed to achieve its carbon emissions reduction obligations by promoting qualifying actions to domestic energy users by 31 December 2012. SSE as a whole delivered 90.9% of its obligation and had a shortfall of 252,168 tCO2. SSE’s shortfall as a percentage of its obligation (9.1%) was smaller than any other OP under CESP.

The particular SSE licensees which failed to meet their obligations were SSE Energy Supply Limited, Southern Electric Gas Ltd, SSEPG (Operations) Ltd, Medway Power Ltd, Keadby Generation Ltd, Greater Gabbard Offshore Windfarm Ltd, Uskmouth Power Company Ltd, Clyde Wind Farm (Scotland) Ltd and Griffin Wind Farm Ltd.

The Authority noted that SSE undertook mitigation activity by May 2013 to mitigate its carbon saving shortfall in full. SSE also over-delivered which resulted in 346 more households receiving measures. The Authority had regard to this in setting the final level of penalty.

A payment of £1.75 million (less a nominal £1 penalty on each of the SSE licensees) will be made by SSE to vulnerable consumers, through the Foundations Independent Living Trust, Energy Action Scotland and the Citizen’s Advice Bureau for use in Wales with the aim of pursuing the following objectives:

• promotion of carbon emissions reduction in domestic homes;

• the promotion of energy efficiency in domestic homes; or

• fuel poverty.

A financial penalty of £1 by each of the SSE licensees is to be made by 17 April 2015.

The case on Ofgem's site

21 Jan 2015: Investigation into whether SSE has infringed the requirements of Chapter II of the Competition Act 1998 and/or Article 102 Treaty on the Functioning of the European Union in respect of points of connection

Type as published: Enforcement case. Published 21 Jan 2015. Closed 7 Nov 2016. Status as published: Closed.

Decision (as Ofgem words it): Decision of the Gas and Electricity Markets Authority to accept binding commitments from SSE plc, following investigation into compliance with Chapter II of the Competition Act 1998 and/or Article 102 of the Treaty on the Functioning of the European Union

The Gas and Electricity Markets Authority (the “Authority”) has confirmed its decision to formally accept commitments from SSE in relation to its investigation. The investigation looked at whether SSE had infringed Chapter II of the Competition Act 1998 and/or Article 102 Treaty on the Functioning of the European Union by abusing a dominant position and putting its competitors at a disadvantage in the electricity connections market in the area covered by SSE’s electricity distribution network in the south of England.

On 22 June 2016, the Authority announced its proposal to accept commitments from SSE in relation to the investigation. Five responses to that consultation were received.

On 3 November 2016, the Authority decided to formally accept SSE’s commitments. The accepted commitments address the competition concerns that the Authority had identified during the course of the investigation. The alternative to accepting commitments would have been to continue the investigation. This would have required the use of significant additional resources before being able to determine whether there had been an infringement of the Competition Act.

Formal acceptance of the commitments by the Authority means that the investigation has been closed. No decision has been taken on whether or not SSE plc had infringed competition rules. The commitments are binding and enforceable under section 31E of the Competition Act 1998.

Further details of the accepted commitments can be found in the Notice of decision to accept binding commitments from SSE plc.

The case on Ofgem's site

14 Oct 2014: Investigation into British Gas’ compliance with its obligations under the electricity supply licence (Standard Licence Condition 12)

Type as published: Enforcement case. Published 14 Oct 2014. Closed 27 Jan 2017. Status as published: Closed.

Decision (as Ofgem words it): Notice of Decision to impose a financial penalty on British Gas following our investigation into its compliance with its obligations under the electricity supply licence (Standard Licence Condition 12)

The Gas and Electricity Markets Authority ("the Authority") has decided to impose a financial penalty on British Gas Trading Limited ("British Gas") following an investigation by Ofgem into its failure to comply with Standard Licence Condition 12 of the Electricity Supply Licence, in relation to advanced meters for non-domestic premises.

Under SLC 12.18 licensees must not install an electricity meter, other than an advanced meter, at relevant premises after 6 April 2009. Under SLC 12.21 licensees must not, from 6 April 2014, supply electricity to any relevant premises other than through an advanced meter. SLC 12.22 states that the prohibition in SLC 12.21 does not apply where the licensee is unable to install or arrange for the installation of any advanced meter at the relevant premises in question despite taking all reasonable steps to do so (for the purposes of SLC 12, ‘relevant premises’ are defined as Non-Domestic Premises where the metering point falls within profile class 5, 6, 7, or 8 as defined by the Balancing and Settlement Code).

The Authority found that British Gas installed electricity meters at a number of relevant premises after the regulatory deadline (6 April 2009) that were not advanced meters, in breach of SLC 12.18. The Authority also found that British Gas was in breach of SLC 12.21 as at 6 April 2014. The Authority found that British Gas failed to take all reasonable steps to install or arrange for the installation of advanced meters at all relevant premises as at 6 April 2014. The Authority was of the view that around 10,000 additional meter points at relevant premises would have been supplied through an advanced meter had British Gas taken all reasonable steps to install or arrange for the installation of advanced meters at those premises.

The Authority considered it appropriate to impose a penalty for this contravention. The penalty of £1 takes into account the fact that British Gas agreed to settle the investigation and to make consumer redress payments of £4.5m (minus £1) to the Carbon Trust. These monies are to be used to help businesses across Great Britain save energy via energy saving audits and advice, and the installation of energy efficiency measures.

Furthermore, British Gas agreed to increased levels of monitoring of the meter points at relevant premises which have not yet been installed with an advanced meter.

The case on Ofgem's site

9 Oct 2014: Investigation into compliance with the Gas and Electricity Consumer Complaints Handling Standards (CHSR) Regulations 2008

Type as published: Enforcement case. Published 9 Oct 2014. Closed 10 Oct 2014. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty following an investigation into compliance by EDF Energy with the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008

Sectoral Case

We have been investigating whether EDF Energy has complied with the Gas and Electricity (Consumer Complaints Handling Standards) Regulations (CHSR) 2008.

The CHSR prescribe standards for the handling of consumer complaints by regulated providers and for the supply of information to consumers about the prescribed standards and levels of compliance with those standards.

The investigation focused on whether EDF Energy’s customer contact centre complied with the requirements of the CHSR.

The Authority has concluded that EDF Energy has breached regulations 7 (1) (a), 4 and 5 of the CHSR between May 2011 and January 2012. EDF Energy has agreed to make a £3m contribution to Citizens Advice Energy Best Deal Extra and Plymouth Citizen’s Advice Bureau.

The Authority considered that the £3m payment offered by EDF Energy to aid consumers will be of greater benefit to energy customers than if a substantial penalty was imposed. Accordingly, The Authority decided that a nominal penalty of £1 should be imposed. The Authority has now issued a notice of its decision to issue a financial penalty.

The regulations breached by EDF Energy required EDF Energy:

to receive, handle and process consumer complaints in an efficient and timely manner (Regulation 7 (1) (a);

electronically record prescribed information when a consumer complaint is received (Regulation 4);

electronically record prescribed information where a consumer complaint has not been resolved by the end of the working day after the day it was received (Regulation 5).

The case on Ofgem's site

3 Jul 2014: Investigation into compliance with obligations under the gas and electricity supply licences (Standard Licence Condition 27.2A) - Notice of decision

Type as published: Enforcement case. Published 3 Jul 2014. Closed 3 Jul 2014. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty on Scottish Power - SLC 27.2A Investigation

Sectoral case

The Authority has confirmed the financial penalty on Scottish Power following the investigation into Scottish Power’s compliance with Standard Licence Conditions 27.2A of its electricity and gas supply licence with respect to cost reflective price differentials.

By way of background, following the Energy Supply Probe, Ofgem introduced SLC 27.2A into the standard conditions of the gas and electricity supply licenses in January 2009. SLC 27.2A requires that any differences in terms and conditions between payment methods for paying charges for the supply of gas/electricity shall reflect the costs to the supplier of the different payment methods. If a licensee intends to set different terms and conditions for different payment methods, the licensee must have a robust process in place which ensures that those differences are complaint with SLC 27.2A. Notably, the licensee must have a sufficiently robust view of the relative costs of the different payment methods.

The Authority has found that Scottish Power failed to take sufficient steps at the time that it set the prices to ensure that the differentials between standard credit and direct debit prices and discounts were compliant with SLC 27.2A over the period 1 September 2009 to 2 December 2012.

The Authority considered it appropriate to impose a penalty on Scottish Power. However, Scottish Power agreed to pay £750,000 in payments to Energy Best Deal. The Authority considered that the payments offered by Scottish to aid consumers will be of greater benefit to energy customers than if a substantial penalty was imposed. Accordingly, the Authority decided that a nominal penalty of £1 should be imposed.

The case on Ofgem's site

2 Jul 2014: Investigation into compliance with obligations under the gas and electricity supply licences (Standard Licence Condition 25) - Notice of Decision

Type as published: Enforcement case. Published 2 Jul 2014. Closed 2 Jul 2014. Status as published: Closed.

Decision (as Ofgem words it): Notice of Decision to impose a financial penalty on EON - SLC 25 Investigation

The Authority has confirmed its decision to impose a financial penalty on E.ON following the investigation into E.ON’s compliance with Standard Licence Conditions 23 and 25 of its electricity and gas supply licence with respect to telephone and face-to-face sales activities.

By way of background, following the Energy Supply Probe, Ofgem put in place a new version of Standard Licence Condition 25 with a view to helping domestic customers make well-informed decisions in response to telephone and face-to-face sales activities. In particular, domestic suppliers are required to provide estimates and comparisons during face-to-face sales activities (with effect from 18 January 2010) and to secure the achievement of an objective in respect of both face-to-face and telesales activities (with effect from 21 October 2009). In summary, the Objective requires domestic suppliers to take all reasonable steps to ensure information provided is complete and accurate, understandable, appropriate and not misleading, and that sales activities are conducted in a fair, transparent, appropriate and professional manner.

The Authority found that E.ON has failed to comply with various of their obligations in this regard over a protracted period, from June 2010 to December 2013.

The Authority considered it appropriate to impose a penalty on E.ON. However, E.ON agreed to pay £12m in payments to vulnerable customers. The Authority considered that the payments offered by E.ON to aid consumers will be of greater benefit to energy customers than if a substantial penalty is imposed. Accordingly, the Authority decided that a nominal penalty of £1 should be imposed.

The case on Ofgem's site

2 Jul 2014: Notice of Decision to impose a financial penalty on EON - SLC 25 Investigation

Type as published: Enforcement case. Published 2 Jul 2014.

Decision for (as Ofgem words it): Investigation into compliance with obligations under the gas and electricity supply licences (Standard Licence Condition 25) - Notice of Decision

The Authority has confirmed its decision to impose a financial penalty on E.ON following the investigation into E.ON’s compliance with Standard Licence Conditions 23 and 25 of its electricity and gas supply licence with respect to telephone and face-to-face sales activities.

By way of background, following the Energy Supply Probe, Ofgem put in place a new version of Standard Licence Condition 25 with a view to helping domestic customers make well-informed decisions in response to telephone and face-to-face sales activities. In particular, domestic suppliers are required to provide estimates and comparisons during face-to-face sales activities (with effect from 18 January 2010) and to secure the achievement of an objective in respect of both face-to-face and telesales activities (with effect from 21 October 2009). In summary, the Objective requires domestic suppliers to take all reasonable steps to ensure information provided is complete and accurate, understandable, appropriate and not misleading, and that sales activities are conducted in a fair, transparent, appropriate and professional manner.

The Authority found that E.ON has failed to comply with various of their obligations in this regard over a protracted period, from June 2010 to December 2013.

The Authority considered it appropriate to impose a penalty on E.ON. However, E.ON agreed to pay £12m in payments to vulnerable customers. The Authority considered that the payments offered by E.ON to aid consumers will be of greater benefit to energy customers than if a substantial penalty is imposed. Accordingly, the Authority decided that a nominal penalty of £1 should be imposed.

The case on Ofgem's site

2 Jul 2014: Notice of decision to impose a financial penalty on Scottish Power - SLC 27.2A Investigation

Type as published: Enforcement case. Published 2 Jul 2014.

Decision for (as Ofgem words it): Investigation into compliance with obligations under the gas and electricity supply licences (Standard Licence Condition 27.2A) - Notice of decision

The Authority has confirmed the financial penalty on Scottish Power following the investigation into Scottish Power’s compliance with Standard Licence Conditions 27.2A of its electricity and gas supply licence with respect to cost reflective price differentials.

By way of background, following the Energy Supply Probe, Ofgem introduced SLC 27.2A into the standard conditions of the gas and electricity supply licenses in January 2009. SLC 27.2A requires that any differences in terms and conditions between payment methods for paying charges for the supply of gas/electricity shall reflect the costs to the supplier of the different payment methods. If a licensee intends to set different terms and conditions for different payment methods, the licensee must have a robust process in place which ensures that those differences are complaint with SLC 27.2A. Notably, the licensee must have a sufficiently robust view of the relative costs of the different payment methods.

The Authority has found that Scottish Power failed to take sufficient steps at the time that it set the prices to ensure that the differentials between standard credit and direct debit prices and discounts were compliant with SLC 27.2A over the period 1 September 2009 to 2 December 2012.

The Authority considered it appropriate to impose a penalty on Scottish Power. However, Scottish Power agreed to pay £750,000 in payments to Energy Best Deal. The Authority considered that the payments offered by Scottish to aid consumers will be of greater benefit to energy customers than if a substantial penalty was imposed. Accordingly, the Authority decided that a nominal penalty of £1 should be imposed.

The case on Ofgem's site

27 Jun 2014: Investigation into the reporting by Npower Limited of electricity supply data under the Renewables Obligation and Feed-in Tariff scheme - Notice of Decision

Type as published: Enforcement case. Published 27 Jun 2014. Closed 27 Jun 2014. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty following an investigation into the reporting by Npower Limited of electricity supply data under the Renewables Obligation and Feed-in Tariff scheme

In September 2013, we opened an investigation into npower’s compliance with its reporting obligations under the Renewables Obligation and Feed-in Tariff scheme .

These provisions are very important as Ofgem relies on licence holders submitting accurate information to carry out its statutory functions and administer environmental programmes, including the RO and FiTs, effectively.

The Authority has concluded that the licensees, npower Limited, npower Northern Limited, npower Direct Limited, and npower Yorkshire Limited breached their reporting requirements under s.32J of the Electricity Act 1989 for the reporting of electricity supply data to Ofgem for the 2010/11 and 2011/12 reporting periods.

The Authority has confirmed its decision to impose a financial penalty of £125,000 .

The penalty of £125,000 was to be made by npower by 11 August 2014. npower missed this deadline and made payment on 21 August 2014. npower paid an additional sum of £328.77 in interest to reflect the late payment of the penalty.