Public beta. Not yet independently reviewed. ProjectWhitehall republishes public records from official sources. It is not an investigation, a legal finding or advice. Registers can be late, incomplete or wrong, and a link between records does not show wrongdoing. Absence of a record does not mean absence of activity. Always check the original source, which we link on every entry. We have already made mistakes and list them all in the corrections log.

ProjectWhitehall

Ofgem compliance and enforcement cases, page 12 of 17

Cases 166 to 180 of 252, newest first, each in Ofgem's words. What this list is and is not, and how it was read, are on the first page of the list.

The status and every other word is Ofgem's, as it stood when we retrieved it. An open case is not a finding. We add no label to a case or a company, and no case is linked to a licence holder, a company page, a donation or a contract.

Cases 166 to 180 of 252. Page 12 of 17. Every row is on one of these pages.

12 Nov 2015: Investigation into Utilita and its compliance with its obligations under Standard Licence Condition 14 (SLC 14) of their gas and electricity supply licences

Type as published: Enforcement case. Published 12 Nov 2015. Closed 12 Nov 2015. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty on Utilita Energy Limited following our investigation into its compliance with its obligations under Standard Licence Condition 14 (SLC 14) of their gas and electricity supply licences

The Authority has confirmed its decision to impose a financial penalty on Utilita Energy Limited (Utilita) following an investigation into its compliance with a number of relevant conditions set out in SLC 14. The provisions of SLC 14 govern when a licensee may block a domestic customer’s request to transfer to another supplier.

• SLC 14.1 sets out a general prohibition stating that licensees must not prevent Proposed Supplier Transfers (PST) except in accordance with the conditions set out in SLC 14.

• SLC 14.4 (c) sets out one of the circumstances in which licensees can legitimately prevent a PST taking place, namely where a customer has not entered into a contract with a proposed new supplier and asks the licensee to prevent the PST from taking place.

• SLC 14.6 provided, at the time of the investigation, that licensees shall ensure that Outstanding Charges of amounts equal to or less than £200 are capable of being assigned to proposed suppliers in accordance with the Debt Assignment Protocol.

• SLC 14.9 requires among other things that when preventing PSTs, licensees send out notices to help customers make informed decisions about who to contact to resolve any issues they might have during the switching process.

• SLC 14.10 provides that, if sub-paragraph 14.4(c) applies and the licensee can legitimately prevent a PST at the customer’s request, the licensee must keep evidence of that request and inform the proposed new supplier that an objection has been raised and the reason given by the customer for making the request.

Utilita has admitted that it breached the SLCs listed above.

We launched our investigation in response to information from a range of sources, including consumer complaints and information provided by the company.

The Authority has confirmed its decision to impose a financial penalty of £1. This is in addition to £450,000 (less £1) that Utilita has agreed to pay to the UK charity StepChange. Utilita will also refund up to £110,000 to customers who lost out financially after being wrongly stopped from switching. Any unclaimed money will go to StepChange.

The case on Ofgem's site

12 Nov 2015: Notice of decision to impose a financial penalty on Utilita Energy Limited following our investigation into its compliance with its obligations under Standard Licence Condition 14 (SLC 14) of their gas and electricity supply licences

Type as published: Enforcement case. Published 12 Nov 2015.

Decision for (as Ofgem words it): Investigation into Utilita and its compliance with its obligations under Standard Licence Condition 14 (SLC 14) of their gas and electricity supply licences

The Authority has confirmed its decision to impose a financial penalty on Utilita Energy Limited following an investigation into its compliance with its obligations under SLC 14.1, SLC 14.4(c), SLC 14.6, SLC 14.9 and SLC 14.10.

The Authority found that Utilita breached the SLCs listed above; Utilita admitted the breaches.

The Authority has confirmed its decision to impose a financial penalty of £1. This is in addition to £450,000 (less £1) that Utilita has agreed to pay to the UK debt charity StepChange. Utilita will also refund up to £110,000 to customers who lost out financially after being wrongly stopped from switching. Any unclaimed money will go to StepChange.

The case on Ofgem's site

15 Oct 2015: Investigation under Chapter I of the Competition Act 1998 and/or Article 101 Treaty on the Functioning of the European Union: Paid online search advertising

Type as published: Enforcement case. Published 15 Oct 2015. Closed 14 Jun 2016. Status as published: Closed.

Decision (as Ofgem words it): Ofgem has decided to transfer a Competition Act investigation to the Competition and Markets Authority

On 15 October 2015, Ofgem announced an investigation to look at whether some price comparison websites have breached competition law in relation to paid online search advertising.

For the avoidance of doubt, this investigation does not affect consumers' ability to use switching sites to get the best energy deal.

The fact that we have opened this investigation does not mean there has been a breach of competition law.

On 13 June 2016, Ofgem decided to transfer the investigation to the Competition and Markets Authority (the CMA). Read our decision below.

The case on Ofgem's site

3 Jun 2015: Economy Energy: Provisional Order

Type as published: Enforcement case. Published 3 Jun 2015. Closed 3 Jun 2015. Status as published: Provisional Order closed.

Decision (as Ofgem words it): Economy Energy: Revocation Order and Notice of Reasons

On 14 February 2014, we issued a provisional order to Economy Energy in accordance with Section 25(2) of the Electricity Act 1989 and section 28(2) of the Gas Act 1986. The Gas and Electricity Markets Authority ('the Authority') has been in discussions with Economy Energy regarding compliance with its obligations under:

a. the standard conditions of the gas and electricity supply licences (collectively referred to as ‘SLC’); and

b. the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008 (‘Complaints Handling Regulations’).

The particular behaviours of concern giving rise to the provisional order are that Economy Energy Domestic Customers are or were:

1. at risk of being off electricity and/or gas supply during cold weather due to Economy Energy not meeting the requirements of the Complaints Handling Regulations and SLC 22.3; and

2. being blocked from switching away from Economy Energy when they requested to do so, for reasons that were not compliant with the provisions of SLC 14 and 14A.

Based on the information received by the Authority, it appears to the Authority that Economy Energy is contravening or is likely to contravene the following relevant condition or requirement (as applicable):

1. SLC 14, 14A, and 22; and

2. Regulations 3, 4, 5, and 7 of the Complaints Handling Regulations.

Provisional orders are issued in certain circumstances in accordance with the statutory framework and where certain conditions are satisfied. Further information regarding provisional orders is contained within our Enforcement Guidelines .

On 25 March 2014 we issued notice of our intention to confirm the provisional order .

On 13 May 2014 we confirmed the provisional order with modifications .

On 12 November 2014 we issued notice of our proposal to revoke provisions of the confirmed Provisional Order .

On 12 December 2014 we issued a Revocation Order , confirming the proposal, revoking the majority of the provisions of the confirmed Provisional Order with two provisions remaining in place. We also issued a Notice setting out the reasons for this decision and the effect.

On 30 April 2015 we issued notice of our proposal to revoke the remaining provisions of the confirmed Provisional Order.

On 3 June 2015 we issued a Revocation Order, confirming the proposal to revoke the remaining provisions of the confirmed Provisional Order. We also issued a Notice setting out the reasons for this decision and the effect.

The confirmed Provisional Order is no longer in place.

The case on Ofgem's site

22 May 2015: Investigation into E.ON’s compliance with its obligations under the gas and electricity supply licences (Standard Licence Conditions 23.6 and 24.3)

Type as published: Enforcement case. Published 22 May 2015. Closed 22 May 2015. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty on E.ON following our investigation into their January 2013 and 2014 price rises

The Authority has confirmed its decision to impose a financial penalty on E.ON following an investigation by Ofgem into E.ON’s compliance with requirements of conditions 23.6 and 24.3 of its gas and electricity supply licences in relation to E.ON’s January 2013 and 2014 price rises.

Under Ofgem obligations, suppliers had to give customers 30 days’ notice of a price rise; this allowed customers the chance to switch before the increase took effect and without incurring exit fees. When considering the breach in relation to the January 2013 price rise, Ofgem considered SLC 23.6, consolidated to 01 December 2012. This set out that when a supplier was notified that a customer wished to terminate their contract, because of the price rise, they were not permitted to apply the higher charges to that customer if they subsequently received notice confirming that another supplier would be taking over supply.

When considering the breach in relation to the January 2014 price rise, Ofgem considered SLC 23.6, consolidated to 31 December 2013. This set out that when a supplier received notice confirming that another supplier would begin to supply the customer within a reasonable period, because of the price rise, the supplier must not apply the higher charges to that customer. The difference being that the customer did not have to contact the supplier.

Condition 24.3 (as was in force at the relevant times) set out that, in such cases as above, the supplier must not charge a termination fee.

The investigation into the breaches relating to the January 2013 price rises was opened in June 2014. The investigation was extended in July 2014 to include the price increase in January 2014 following further relevant information that came to light.

E.ON has admitted that it breached the SLCs listed above and the Authority also found that E.ON breached the SLCs listed above.

The Authority has confirmed its decision to impose a financial penalty of £1. This is in addition to £7.75 million (less £1) in redress that E.ON has paid to Citizens Advice Energy Best Deal Extra. This redress will be used to provide one-to-one energy advice to vulnerable consumers across Scotland, England and Wales.

The case on Ofgem's site

22 May 2015: Notice of decision to impose a financial penalty on E.ON following our investigation into their January 2013 and 2014 price rises

Type as published: Enforcement case. Published 22 May 2015.

Decision for (as Ofgem words it): Investigation into E.ON’s compliance with its obligations under the gas and electricity supply licences (Standard Licence Conditions 23.6 and 24.3)

The Authority has confirmed its decision to impose a financial penalty on E.ON following an investigation by Ofgem into E.ON’s compliance with requirements of conditions 23.6 and 24.3 of its gas and electricity supply licences in relation to E.ON’s January 2013 and 2014 price rises.

E.ON has admitted that it breached the SLCs listed above and the Authority also found that E.ON breached the SLCs listed above.

The Authority has confirmed its decision to impose a financial penalty of £1. This is in addition to £7.75 million (less £1) in redress that E.ON has paid to Citizens Advice Energy Best Deal Extra. This redress will be used to provide one-to-one energy advice to vulnerable consumers across Scotland, England and Wales.

The case on Ofgem's site

21 May 2015: GF Power Peaking Ltd: Investigation into whether there has been a contravention of Rule 5.13.1(b) of the Capacity Market Rules

Type as published: Enforcement case. Published 21 May 2015. Closed 26 Aug 2015. Status as published: Closed.

1. In May 2015, Ofgem opened an investigation into GF Power Peaking Ltd’s compliance with Rule 5.13.1 (b) of the Capacity Market Rules.

2. In particular Ofgem investigated whether GF Power Peaking Ltd provided false or misleading information to the Delivery Body regarding whether it had obtained all relevant planning consents in relation to certain Capacity Market Units (CMU’s) which participated in the T-4 capacity Auction in December 2014.

3. We have decided to close the investigation as GF Power Peaking has provided Ofgem with information which satisfactorily confirms that there was not a breach of the Capacity Market Rules.

The case on Ofgem's site

21 May 2015: Power Balancing Services Ltd: Investigation into whether there has been a contravention of Rule 5.13.1(b) of the Capacity Market Rules

Type as published: Enforcement case. Published 21 May 2015. Closed 26 Aug 2015. Status as published: Closed.

1. In May 2015, Ofgem opened an investigation into Power Balancing Services Ltd’s compliance with Rule 5.13.1 (b) of the Capacity Market Rules.

2. In particular Ofgem investigated whether Power Balancing Services Ltd provided false or misleading information to the Delivery Body regarding whether it had obtained all relevant planning consents in relation to certain Capacity Market Units (CMU’s) which participated in the T-4 capacity Auction in December 2014.

3. We have decided to close the investigation as Power Balancing Services Ltd has provided Ofgem with information which satisfactorily confirms that there was not a breach of the Capacity Market Rules.

The case on Ofgem's site

21 Apr 2015: Investigation into Spark Energy's compliance with its gas and electricity supply licences and the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008

Type as published: Enforcement case. Published 21 Apr 2015. Closed 21 Apr 2015. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty on Spark Energy following our February 2015 investigation

We investigated whether Spark Energy Supply Ltd ("Spark") complied with the requirements of Standard Supply Licence Conditions (SLCs) 14, 21B, 22, 22C, 23, and 27 of its gas and electricity supply licence, and with the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008 (CHSR).

• SLC 14 sets out the provisions around domestic customer switching. The only permissible reasons for objecting to a request to switch a domestic supply (SLC14.4) are relevant contractual agreement, outstanding charges or transfers initiated in error and, for electricity licensees only, if the new supplier has not applied for all relevant meter points on the same working day.

• SLC 21B requires suppliers to take all reasonable steps to obtain and reflect meter readings into a customer bill or statement of account.

• SLC 22 sets out provisions relating to the duty to offer and supply power under a domestic supply contract.

• SLCs 22C and 23 set out provisions on the operation of the contract between the supplier and customer, including imposing obligations on the supplier in relation to certain variations to supply contracts.

• SLC 27 sets out provisions relating to direct debit management and calculations, and as to final bills or statements of account in case of transfer or termination of the domestic supply contract.

• The CHSR came into force on 1 October 2008. These require suppliers to establish in-house systems, processes and procedures to receive and record all complaints from customers.

We launched our investigation in response to a Consumer Futures referral, consumer complaints, and information Spark provided in response to Ofgem correspondence.

Spark has admitted that it breached the SLCs and CHSRs listed above. The Authority also finds that Spark breached the SLCs and the CHSRs listed above.

The Authority decided to impose a financial penalty of £1. This is in addition to £250,000 (less £1) in redress that Spark has agreed to pay in equal shares to Citizens Advice Scotland and Citizens Advice (covering England and Wales). This redress will be used to provide help and advice to energy consumers.

The case on Ofgem's site

21 Apr 2015: Notice of decision to impose a financial penalty on Spark Energy following our February 2015 investigation

Type as published: Enforcement case. Published 21 Apr 2015.

Decision for (as Ofgem words it): Investigation into Spark Energy's compliance with its gas and electricity supply licences and the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008

We investigated whether Spark Energy Supply Ltd ("Spark") complied with the requirements of Standard Supply Licence Conditions (SLCs) 14, 21B, 22, 22C, 23, and 27 of its gas and electricity supply licence, and with the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008 (CHSR).

Spark has admitted that it breached the SLCs and CHSRs listed above. The Authority found that Spark breached the SLCs and the CHSRs listed above.

The Authority decided to impose a financial penalty of £1. This is in addition to £250,000 (less £1) in redress that Spark has agreed to pay in equal shares to Citizens Advice Scotland and Citizens Advice (covering England and Wales). This redress will be used to provide help and advice to energy consumers.

The case on Ofgem's site

26 Mar 2015: Notice of decision to impose a financial penalty following an investigation into compliance by InterGen with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

Type as published: Enforcement case. Published 26 Mar 2015. Closed 26 Mar 2015.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty following an investigation into compliance by InterGen with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

The Authority has decided to impose a financial penalty on InterGen following an investigation into the company’s compliance with its obligations under Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009.

The Community Energy Saving Programme ("CESP") was a policy, set down in legislation, designed to improve domestic energy efficiency standards in the most deprived geographical areas across Great Britain. The relevant legislation was the Electricity and Gas (Community Energy Saving Programme) Order 2009 ("CESP Order"). Under Article 14(1) of the CESP Order, generators and suppliers had to achieve their carbon emissions reduction obligation by promoting qualifying actions to domestic energy users in low income areas.

The Authority found that InterGen breached Article 14(1) of the CESP Order having failed to achieve its carbon emissions reduction obligations by promoting qualifying actions to domestic energy users by 31 December 2012. InterGen failed to meet by 31 December 2012, its carbon emissions reduction obligation mandated under Article 14(1) of the CESP Order. The particular InterGen licensees which failed to meet their obligations were Rocksavage Power Company Ltd, Coryton Energy Company Ltd, and Spalding Energy Company Ltd. InterGen as a whole delivered 6.4% of its obligation and had a shortfall of 489,776 tCO2. InterGen’s shortfall as a percentage of its obligation (93.6%) was greater than any other OP under CESP.

The Authority noted that although InterGen undertook some mitigation activity by May 2013 to mitigate its carbon saving shortfall, InterGen did not mitigate its shortfall in full. InterGen had 203,276 tCO2 (38.8% of its obligation) still undelivered. The Authority had regard to this in setting the level of penalty.

A nominal financial penalty of £1 each will be paid by Rocksavage Power Company Ltd, Coryton Energy Company Ltd and Spalding Energy Company Ltd on the basis that InterGen will pay £11 million (less the £3 financial penalties) in consumer redress. The payments of consumer redress are to be made to:

New Gorbals Housing Association (£4.8 million) for the implementation of a gas-powered heating scheme and other measures to over 400 housing units in Glasgow; and

National Energy Action (NEA) (£6.2 million) divided between two funds: the Technical Innovation Fund (£3.2million) and the Warm Zones Fund (£3.0 million). These funds will deliver measures to over 1500 households.

The redress payments are to be made at a date to be agreed with the Authority but which shall not be later than 30 April 2015. The financial penalty of £3 is to be paid by 8 May 2015.

The case on Ofgem's site

18 Mar 2015: Investigation into UK Capacity Reserve Limited’s compliance with Rule 5.13.1(b) of the Capacity Market Rules

Type as published: Enforcement case. Published 18 Mar 2015. Closed 18 Mar 2015. Status as published: Closed.

Decision (as Ofgem words it): Notice of Decision into whether UK Capacity Reserve Limited (UKCR) complied with the requirements of Rule 5.13.1(b) of the Capacity Market Rules

The Authority has decided that UK Capacity Reserve Limited ("UKCR") contravened relevant requirements, defined under section 25(8) of the Electricity Act 1989, namely the requirements of Rule 5.13.1(b) of the Capacity Market Rules.

The Capacity Market is part of the Government’s reforms intended to ensure sufficient capacity on the system to provide a reliable electricity supply. National Grid will run an annual auction to decide which generators and providers of demand side response will be awarded a capacity agreement, in return for providing capacity at times of system stress. Companies had to submit applications for the first such auction in November 2014 and National Grid awarded the contracts in January 2015.

The Authority found that UKCR submitted inaccurate information when applying to be part of the 2014’s capacity auction. As a result the Authority found UKCR to have contravened a relevant requirement, namely Rule 5.13.1(b) of the Capacity Market Rules in respect of 11 of its generating units. As a result, these generating units have been excluded from submission for capacity auctions taking place in the next two years. UKCR has accepted the Authority’s finding.

The case on Ofgem's site

16 Mar 2015: Notice of decision to impose a financial penalty following an investigation into compliance by Drax with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

Type as published: Enforcement case. Published 16 Mar 2015. Closed 16 Mar 2015. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty following an investigation into compliance by Drax with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

The Authority has decided to impose a financial penalty on Drax following an investigation into the company’s compliance with its obligations under Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009.

The Community Energy Saving Programme ("CESP") was a policy, set down in legislation, designed to improve domestic energy efficiency standards in the most deprived geographical areas across Great Britain. The relevant legislation was the Electricity and Gas (Community Energy Saving Programme) Order 2009 ("CESP Order"). Under Article 14(1) of the CESP Order, generators and suppliers had to achieve their carbon emissions reduction obligation by promoting qualifying actions to domestic energy users in low income areas.

The Authority found that Drax breached Article 14(1) of the CESP Order having failed to achieve its carbon emissions reduction obligations by promoting qualifying actions to domestic energy users by 31 December 2012. Drax delivered 37.1% of its obligation and had a significant shortfall of 562,826 tCO2 or 62.9% of its obligation.

Drax will pay a penalty of £5 million. They will also pay £20 million in consumer redress to National Energy Action with the aim of pursuing the following objectives:

the promotion of energy efficiency in domestic homes;

the alleviation of fuel poverty;

the reduction of carbon emissions in domestic homes.

Drax has also separately arranged delivery of energy efficiency measures to the value of £3 million by 31 October 2016.

The case on Ofgem's site

5 Mar 2015: Investigation into British Gas’ compliance with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

Type as published: Enforcement case. Published 5 Mar 2015. Closed 5 Mar 2015. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty on British Gas following our investigation into its compliance with Article 14(1) of the Electricity and Gas (Community Energy Saving Programme) Order 2009

The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on British Gas for its failure to meet its obligations under Article 14(1) of the Electricity and Gas (Carbon Emissions and Community Energy Saving) Order 2009 ("CESP Order"), and consideration by the Authority of representations or objections received on its proposed penalty. These representations or objections are discussed in the Annex to the Penalty Notice.

The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £1 on British Gas, on the basis that British Gas has made a payment of £10.6 million (less the £1 financial penalty) in consumer redress to the British Gas Energy Trust ("BGET"). The BGET shall distribute the redress monies to organisations which pursue any or all of the following objectives for vulnerable customers:

the promotion of energy efficiency in domestic homes;

the alleviation of fuel poverty;

the reduction of carbon emissions in domestic homes.

Further details can be found in the Penalty Notice.

The case on Ofgem's site

5 Mar 2015: Investigation into British Gas’ compliance with Article 9(1) and Article 9(1A) of the Electricity and Gas (Carbon Emissions Reduction) Order 2008 (as amended)

Type as published: Enforcement case. Published 5 Mar 2015. Closed 5 Mar 2015. Status as published: Closed.

Decision (as Ofgem words it): Notice of decision to impose a financial penalty following an investigation into compliance by British Gas with Article 9(1) and Article 9(1A) of the Electricity and Gas (Carbon Emissions Reduction) Order 2008 (as amended)

The Authority has decided to impose a financial penalty on British Gas following an investigation into the company’s compliance with its obligations under Article 9(1) and Article 9(1A) of the Electricity and Gas (Carbon Emissions Reduction) Order 2008 (as amended).

The Carbon Emissions Reduction Target (CERT) was a policy, set down in legislation, designed to improve domestic energy efficiency standards across households in Great Britain. The policy was designed to contribute to the UK’s legally binding emissions reduction commitments. The relevant legislation was the Electricity and Gas (Carbon Emissions Reduction) Order 2008, as amended ("CERT Order"). Article 9(1) of the CERT Order required that certain gas and electricity suppliers must achieve their carbon emissions reduction obligations by promoting qualifying actions to domestic energy users in Great Britain. Article 9(1A) of the CERT Order required those suppliers to achieve a defined proportion of that obligation by promoting insulation measures.

The Authority noted that British Gas initially had an obligation to promote carbon savings equivalent to 96,279.607 ktCO2. Under Article 9(1), as a group, British Gas delivered 98.9% of its overall CERT target and had a shortfall of 1,075.111 ktCO2 at 31 December 2012. Under Article 9(1A), as a group, it delivered 95.5% of its Insulation Obligation target of 24,119.192 ktCO2 and had a shortfall of 1,089.622 ktCO2 at 31 December 2012. The shortfall of British Gas’s overall CERT target was incurred entirely against its Insulation Obligation. British Gas accepts that it breached Articles 9(1) and 9(1A) of the CERT Order.

The Authority noted that British Gas undertook mitigation action equivalent to the volume of its shortfall associated with not achieving the carbon reduction target promptly by February 2013 (for both the overall CERT obligation and IO). British Gas also over-delivered during CERT mitigation. The Authority had regard to this in setting the level of penalty.

A payment of £500,000 (less a nominal £1 penalty) has been made by British Gas to the British Gas Energy Trust ("BGET"). The BGET shall distribute the redress monies to organisations which pursue any or all of the following objectives for vulnerable customers:

• the promotion of energy efficiency in domestic homes;

• the alleviation of fuel poverty;

• the reduction of carbon emissions in domestic homes.

A financial penalty of £1 is to be made by British Gas by 17 April 2015.

The case on Ofgem's site