Ofgem compliance and enforcement cases, page 11 of 17
Cases 151 to 165 of 252, newest first, each in Ofgem's words. What this list is and is not, and how it was read, are on the first page of the list.
Cases 151 to 165
Source stamp: OFGEM COMPLIANCE AND ENFORCEMENT CASES / RETRIEVED 24 NOV 2026 / NO LINK MADEThe status and every other word is Ofgem's, as it stood when we retrieved it. An open case is not a finding. We add no label to a case or a company, and no case is linked to a licence holder, a company page, a donation or a contract.
Cases 151 to 165 of 252. Page 11 of 17. Every row is on one of these pages.
29 Jul 2016: Investigation into SSE and its compliance with its obligations under the gas and electricity supply licences (Standard Licence Conditions 25C, 27.1, 28.1, 27.5, 27.6 and 27.8)
Type as published: Enforcement case. Published 29 Jul 2016. Closed 20 Nov 2017. Status as published: Closed.
Decision (as Ofgem words it): Decision of the Gas and Electricity Markets Authority to close its investigation into SSE’s compliance with the requirements of conditions 25C, 27.1, 27.5, 27.6, 27.8 and 28.1 of its gas and electricity supply licences
The Gas and Electricity Markets Authority ("the Authority") has decided to close its investigation into SSE’s compliance with its obligations under the gas and electricity supply licences (Standard Licence Conditions 25C, 27.1, 28.1, 27.5, 27.6 and 27.8).
The decision was taken following satisfactory implementation of improvement actions agreed between the Authority and SSE.
Further details can be found in the decision document.
4 Jul 2016: Investigation into Extra Energy Supply Ltd and its compliance with its obligations under the gas and electricity supply licences (SLC 7B, 14, 21B, 25C, 27, 31A) and with the Consumer Complaints Handling Standards Regulations 2008
Type as published: Enforcement case. Published 4 Jul 2016. Closed 5 Dec 2018. Status as published: Closed.
Decision (as Ofgem words it): Decision to close the investigation into Extra Energy Supply Ltd and its compliance with its obligations under the gas and electricity supply licences (SLC 7B, 14, 21B, 25C, 27, 31A) and with the Consumer Complaints Handling Standards Regulations 2008
Extra Energy Supply Limited ("Extra") ceased trading on 21 November 2018 and its licences to supply gas and electricity were revoked as of 25 November 2018.
As a result, the Investigation into Extra and its compliance with its obligations under its gas and electricity supply licences, SLC 7B, 14, 21B, 25C, 27, 31A and with the Consumer Complaints Handling Standards Regulations 2008, has closed.
We were investigating whether Extra breached numerous licence conditions and Consumer Complaints Handling Standards relating to treating customers fairly, frequency of billing, timely provision of final bills, provision of annual statements, return of credit balances, handling meter readings appropriately, transfer blocking, and complaints and call handling.
Extra’s customers have been transferred to Scottish Power under the Supplier of Last Resort (SoLR) process. If you would like any further information regarding the SoLR process and how this is being managed please see: Extra Energy customers: Your questions on new supplier Scottish Power .
8 Jun 2016: Investigation into ScottishPower’s compliance with Standards of Conduct (SLC 25C), SLC 27 (provision of final bills), and the Gas and Electricity (Consumer Complaints Handling Standards) Regulations (CHRs) 2008
Type as published: Enforcement case. Published 8 Jun 2016. Closed 8 Jun 2016. Status as published: Closed.
Decision (as Ofgem words it): Notice of decision to impose a financial penalty on ScottishPower following our investigation into its compliance with Standards of Conduct (SLC25C), SLC27, and the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008
The Gas and Electricity Markets Authority (“the Authority”) has confirmed its decision to impose a financial penalty on ScottishPower for failure to comply with SLCs 25C (Standards of Conduct) and 27.17 of the Electricity and Gas Supply Licences, and for failure to comply with Regulations 3(2); 4(1); 5(1) and 5(2)(a)-(b); and 7(1)(a)-(b) of the Gas and Electricity (Consumer Complaint Handling Standards) Regulations 2008 (CHRs).
SLC25C (Standards of Conduct) requires suppliers to take all reasonable steps to achieve the Standards of Conduct, and to ensure that the Standards are interpreted and applied consistently with the Customer Objective of treating customers fairly.
SLC 27.17 requires suppliers to take all reasonable steps to issue a final bill or statement of account within 6 weeks of termination of supply
CHR 3(2) requires suppliers to adhere to their own complaints handling procedure
CHR 4(1) requires suppliers to record complaints upon receipt
CHR 5(1) and 5(2)(a)-(b) requires suppliers to record the handling of complaints
CHR 7(1)(a) concerns the requirement of timely and efficient receipt, handling and processing of complaints
CHR 7(1)(b) requires suppliers to allocate and maintain resources reasonably required for timely, efficient and compliant complaints processing
The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £1 on ScottishPower. This is an addition to £18 million (less £1) that the ScottishPower has agreed to pay in consumer redress. Of the proposed redress, up to £15 million will go to vulnerable customers directly affected by ScottishPower’s failings. At least £3 million will go to a cause to be agreed between ScottishPower and the Authority.
Further details can be found in the final penalty notice.
15 Mar 2016: Investigation under Chapter I of the Competition Act 1998 and/or Article 101 Treaty on the Functioning of the European Union: Commission rates
Type as published: Enforcement case. Published 15 Mar 2016. Closed 15 Mar 2016. Status as published: Closed.
On 9 February 2015, Ofgem announced an investigation into whether two or more companies providing a supporting service for the energy industry had breached competition law. Specifically, the investigation looked into whether two or more parties had shared information on the commission rates charged to energy suppliers.
On 15 March 2016 Ofgem closed its investigation and published the open letter below providing further details.
22 Feb 2016: Investigation into British Gas Trading Limited and its compliance with SLC 7A, 7B, 14, 14A and 21B and with the Consumer Complaints Handling Standards Regulations 2008
Type as published: Enforcement case. Published 22 Feb 2016. Closed 29 Jun 2017. Status as published: Closed.
Decision (as Ofgem words it): Notice of decision to impose a financial penalty on British Gas Trading Limited following our investigation into its compliance SLC 7A, 7B, 14, 14A and 21B and with the Consumer Complaints Handling Standards Regulations 2008
The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on British Gas Trading Limited ("British Gas") following an investigation by Ofgem into its failure to comply with requirements under conditions 7A, 7B, 14A and 21B of its gas and electricity supply licenses and Regulations 3(2), 7(1)(a) and 7(1)(b) of the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008 (CHRs).
Conditions 7A, 14A and 21B contain safeguards relating to supply to micro business consumers, as well as obligations on (non-domestic) customer transfers and billing.
Condition 7B (Standards of Conduct) requires suppliers to take all reasonable steps to achieve the Standards of Conduct (SOC), and to ensure they interpret and apply the SOC in a manner consistent with the Customer Objective of ensuring that each micro-business customer is treated fairly.
CHR 3(2) sets out provisions relating to the duty upon a supplier to comply with its own complaints handling procedure in relation to each consumer complaint it receives.
CHR 7(1)(a) sets out the duty upon a supplier to receive, handle and process consumer complaints in an efficient and timely manner.
CHR 7(1)(b) sets out the duty upon a supplier to allocate and maintain sufficient resources for the efficient and timely handling of complaints and to enable the supplier’s other obligations under the CHRs to be met.
The Authority considered it appropriate to impose a penalty for these contraventions. The penalty of £1 takes into account the fact that British Gas agreed to settle the investigation and to make consumer redress payments of £9.5 million (minus £1). British Gas will make consumer redress payments both to micro-business customers directly affected by its failings, and to the Money Advice Trust (which provides the Business Debtline service). The redress payments to Business Debtline will be used to provide debt advice services to business customers who are experiencing difficulties in paying their energy bills.
Further details can be found in the final Penalty Notice.
27 Jan 2016: Investigation into npower’s compliance with Standards of Conduct (Standard Licence Condition 25C), Standard Licence Condition 27 (provision of final bills), and the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008
Type as published: Enforcement case. Published 27 Jan 2016. Closed 27 Jan 2016. Status as published: Closed.
Decision (as Ofgem words it): Notice of decision to impose a financial penalty on npower following our investigation into its compliance with Standards of Conduct (SLC25C), SLC27 (final bills), and the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008
The Gas and Electricity Markets Authority (“the Authority”) has confirmed its decision to impose a financial penalty on npower Direct Ltd, npower Ltd, npower Northern Ltd, npower Northern Supply Ltd, npower Yorkshire Supply Ltd, npower Yorkshire Ltd and npower Gas Ltd. The Authority found that they failed to comply with Standard Licence Conditions 25C (Standards of Conduct) and 27.17 of the Electricity and Gas Supply Licences, and Regulations 3(2); 4(6)(a)-(d); 5(1); 6(1); 7(1)(a)-(b); and 10(2) of the Gas and Electricity (Consumer Complaint Handling Standards) Regulations 2008.
SLC25C (Standards of Conduct) requires suppliers to take all reasonable steps to achieve the Standards of Conduct and to ensure that the Standards are interpreted and applied consistently with the Customer Objective which is to treat customers fairly.
SLC 27.17 requires suppliers to take all reasonable steps to issue a final bill or statement of account within 6 weeks of termination of supply
CHR 3(2) requires suppliers to adhere to their own complaints handling procedure
CHR 4(6)(a)-(d) covers the recording and treatment of repeat/unresolved complaints
CHR 5(1) requires suppliers to record the handling of complaints
CHR(6)(1) requires suppliers to signpost the redress scheme of the Ombudsman after 56 days
CHR 7(1)(a) concerns the requirement of timely and efficient receipt, handling and processing of complaints
CHR 7(1)(b) requires suppliers to allocate and maintain resources reasonably required for timely, efficient and compliant complaints processing
CHR 10(2) requires suppliers to signpost their complaints procedure and offer to provide a copy to customers free of charge
The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £1 on each of the seven npower companies (total penalty £7). This is in addition to £26m (less £7) that the npower companies agreed to pay in consumer redress. The redress will go to customers directly affected by the npower companies’ failings, and to charitable organisations for the benefit of domestic energy consumers. This redress must be paid to customers by the 30 June 2016 and to charitable organisations by 31 July 2016.
Furthermore, the npower companies agreed to meet targets on billing and complaints handling by 30 June 2016. If they fail to achieve these targets, the npower companies will stop all proactive domestic selling until they do so.
Further details can be found in the final penalty notice.
27 Jan 2016: Notice of decision to impose a financial penalty on npower following our investigation into its compliance with Standards of Conduct (SLC25C), SLC27 (final bills), and the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008
Type as published: Enforcement case. Published 27 Jan 2016.
Decision for (as Ofgem words it): Investigation into npower’s compliance with Standards of Conduct (Standard Licence Condition 25C), Standard Licence Condition 27 (provision of final bills), and the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008
The Gas and Electricity Markets Authority (“the Authority”) has confirmed its decision to impose a financial penalty on npower Direct Ltd, npower Ltd, npower Northern Ltd, npower Northern Supply Ltd, npower Yorkshire Supply Ltd, npower Yorkshire Ltd and npower Gas Ltd. The Authority found that they failed to comply with Standard Licence Conditions 25C (Standards of Conduct) and 27.17 of the Electricity and Gas Supply Licences, and Regulations 3(2); 4(6)(a)-(d); 5(1); 6(1); 7(1)(a)-(b); and 10(2) of the Gas and Electricity (Consumer Complaint Handling Standards) Regulations 2008.
SLC25C (Standards of Conduct) requires suppliers to take all reasonable steps to achieve the Standards of Conduct and to ensure that the Standards are interpreted and applied consistently with the Customer Objective which is to treat customers fairly.
SLC 27.17 requires suppliers to take all reasonable steps to issue a final bill or statement of account within 6 weeks of termination of supply
CHR 3(2) requires suppliers to adhere to their own complaints handling procedure
CHR 4(6)(a)-(d) covers the recording and treatment of repeat/unresolved complaints
CHR 5(1) requires suppliers to record the handling of complaints
CHR(6)(1) requires suppliers to signpost the redress scheme of the Ombudsman after 56 days
CHR 7(1)(a) concerns the requirement of timely and efficient receipt, handling and processing of complaints
CHR 7(1)(b) requires suppliers to allocate and maintain resources reasonably required for timely, efficient and compliant complaints processing
CHR 10(2) requires suppliers to signpost their complaints procedure and offer to provide a copy to customers free of charge
The Authority considered it appropriate to impose a financial penalty for these contraventions. The Authority decided to impose a financial penalty of £1 on each of the seven npower companies (total penalty £7). This is in addition to £26m (less £7) that the npower companies agreed to pay in consumer redress. The redress will go to customers directly affected by the npower companies’ failings, and to charitable organisations for the benefit of domestic energy consumers. This redress must be paid to customers by the 30 June 2016 and to charitable organisations by 31 July 2016.
Furthermore, the npower companies agreed to meet targets on billing and complaints handling by 30 June 2016. If they fail to achieve these targets, the npower companies will stop all proactive domestic selling until they do so.
Further details can be found in the final penalty notice.
18 Dec 2015: Investigation into BES and its compliance with its obligations under Standard Licence Conditions 7A, 7B, 7, 14 and 21B and with CHSR 2008
Type as published: Enforcement case. Published 18 Dec 2015. Closed 18 Dec 2015. Status as published: Closed.
Decision (as Ofgem words it): Notice of decision to impose a financial penalty on BES following our investigation into its compliance with its obligations under the gas and electricity supply licences (Standard Licence Conditions 7A, 7B, 7, 14 and 21B) and with the Gas and Electricity
We investigated whether BES Commercial Electricity Ltd and Business Energy Solutions Ltd (together referred to as "BES") complied with the requirements of Standard Licence Conditions (SLCs) 7A, 7B, 7 and 14 of their gas and electricity supply licences and with Regulations 4 and 5 of the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008 (the CHSRs).
The Authority found that BES breached the following relevant conditions and requirements:
SLC 7A.4(b) – Supply to Micro Business Consumers – These provisions require that, before a licensee enters into a Micro Business Consumer Contract, it must take all reasonable steps to bring the Principal Terms of the proposed contract to the attention of the consumer and ensure that the information is communicated in plain and intelligible language. These conditions were breached for the period 8 June 2010 to 12 July 2015 (Breaches 1 and 2).
SLC 7B – Customer Objective and Standards of Conduct for non-domestic supply activities – These provisions require that the licensee takes all reasonable steps to achieve the Standards of Conduct and apply the Standards of Conduct in a manner consistent with the Customer Objective of ensuring that each Micro Business Consumer is treated fairly. This condition was breached for the periods 26 August 2013 to 12 July 2015 (Breach 3) in relation to failure to communicate Principal Terms and 26 August 2013 to 14 August 2014 (Breach 4) in relation to Statement of Renewal letters.
SLC 7.6A(c) – Terms of Contracts and Deemed Contracts – These provisions state that a deemed contract must not require a customer to give any form of notice before they are able to change supplier, and were breached for the period 23 October 2013 to 9 June 2014 (Breach 5).
SLC 14 – Non-Domestic Customer Transfer Blocking – These provisions state that a licensee must not prevent a Proposed Supplier Transfer except in accordance with certain specific provisions, one of which being that the licensee’s Contract with that customer allows the licensee to prevent the transfer. Contract is a defined term within SLC 1 and the definition states that a Contract does not include a Deemed Contract. This SLC was breached for the period 14 November 2012 to 9 June 2014 (Breach 6).
Regulations 4 and 5 of the CHSRs. These regulations place requirements on regulated providers in relation to handling consumer complaints, and were breached for the period 1 January 2013 to 31 October 2014 (Breach 7).
BES admitted that it breached the relevant conditions and requirements set out above and co-operated with the Authority’s investigation. BES made improvements in those areas which were the subject of this investigation.
The investigation also looked at a potential breach of SLC 21B in relation to accurate billing, but there was no finding of breach in relation to this SLC.
The Authority decided to impose a financial penalty of £2 on BES (£1 on each licensee) for these contraventions.
The penalty takes into account the fact that BES agreed to pay £980,000 in total by way of settlement of this case.
This total figure includes compensation totalling £311,000 which BES has undertaken to pay to consumers affected by the breaches. BES has also made a consumer redress payment of £669,000 less the penalty sum of £2) to the charity, The Money Advice Trust (Business Debtline). This redress payment is to fund specific projects through which Business Debtline will provide debt advice services to business customers who are experiencing difficulties in paying their energy bills. BES has undertaken to make a second payment to this charity following completion of its arrangements for contacting and paying compensation to customers if there is any residual sum arising from circumstances where it was not possible to contact a customer due compensation.
BES also agreed to contact all those customers who have contacted them previously in relation to any matters relevant to Breaches 1 to 3 to explain its failings and to offer those customers the opportunity to terminate their contract, should they wish to, without a termination fee being imposed.
18 Dec 2015: Notice of decision to impose a financial penalty on BES following our investigation into its compliance with its obligations under the gas and electricity supply licences (Standard Licence Conditions 7A, 7B, 7, 14 and 21B) and with the Gas and Electricity
Type as published: Enforcement case. Published 18 Dec 2015.
Decision for (as Ofgem words it): Investigation into BES and its compliance with its obligations under Standard Licence Conditions 7A, 7B, 7, 14 and 21B and with CHSR 2008
We investigated whether BES Commercial Electricity Ltd and Business Energy Solutions Ltd (together referred to as "BES") complied with the requirements of Standard Licence Conditions (SLCs) 7A, 7B, 7 and 14 of their gas and electricity supply licences and with Regulations 4 and 5 of the Gas and Electricity (Consumer Complaints Handling Standards) Regulations 2008 (the CHSRs).
BES admitted that it breached the relevant conditions and requirements set out above and co-operated with the Authority’s investigation. BES made improvements in those areas which were the subject of this investigation.
The investigation also looked at a potential breach of SLC 21B in relation to accurate billing, but there was no finding of breach in relation to this SLC.
The Authority has confirmed its decision to impose a financial penalty of £2 on BES (£1 on each licensee) for these contraventions.
The penalty takes into account the fact that BES agreed to pay £980,000 in total by way of settlement of this case.
This total figure includes compensation totalling £311,000 which BES has agreed to pay to customers affected by the breaches. BES has also a made consumer redress payment of £669,000 (less the penalty sum of £2) to the charity, The Money Advice Trust (Business Debtline). This redress payment is to fund specific projects through which Business Debtline will provide debt advice services to business customers who are experiencing difficulties in paying their energy bills. BES has undertaken to make a second payment to this charity following completion of its arrangements for contacting and paying compensation to customers.
BES also agreed to contact all those customers who have contacted them previously in relation to any matters relevant to breaches 1 to 3, as set out in the Notice of Decision, to explain its failings and to offer those customers the opportunity to terminate their contract, should they wish to, without a termination fee being imposed.
17 Dec 2015: Investigation into E.ON’s compliance with its obligations under the electricity supply licence (Standard Licence Condition 12)
Type as published: Enforcement case. Published 17 Dec 2015. Closed 17 Dec 2015. Status as published: Closed.
Decision (as Ofgem words it): Notice of decision to impose a financial penalty on E.ON following an investigation into its compliance with Standard Licence Condition 12 of the Electricity Supply Licence
The Gas and Electricity Markets Authority ("the Authority") has confirmed its decision to impose a financial penalty on E.ON UK Plc and E.ON Energy Solutions Ltd (together referred to as "E.ON") following an investigation by Ofgem into its failure to comply with Standard Licence Condition 12 of the Electricity Supply Licence (SLC 12), in relation to advanced meters for non-domestic premises.
Under SLC 12.21 licensees must not, from 6 April 2014, supply electricity to any relevant premises other than through an advanced meter. SLC 12.22 states that this prohibition does not apply where the licensee is unable to install or arrange for the installation of any advanced meter at the relevant premises in question, despite taking all reasonable steps to do so.
The Authority found that, as at 6 April 2014, E.ON was supplying electricity to relevant premises, through 7,011 meter points, other than through an advanced meter and that it was not able to demonstrate that it had been unable to install, or arrange for the installation of, an advanced meter at those premises despite taking all reasonable steps to do so, in breach of SLC 12.21. The investigation focussed on the extent to which E.ON took, or failed to take, all reasonable steps.
The Authority considered it appropriate to impose a penalty for this contravention. The penalty took into account the fact that E.ON was unable to demonstrate that it had taken all reasonable steps to install or arrange for the installation of advanced meters at those 7,011 relevant meter points. The investigation invited E.ON to demonstrate that it had taken all reasonable steps to install advanced meters at all outstanding premises as at 6 April 2014. It was unable to do so. The Authority concluded that E.ON’s inability to demonstrate that it had, for example, effectively planned for and monitored its advanced meter roll-out, ownership within the business for compliance with the obligation, and sufficient management oversight meant that it did not take all reasonable steps to meet the obligation.
In the circumstances, the Authority decided to confirm the financial penalty of £2 on E.ON. This in addition to £7million (less £2) that E.ON agreed to pay in consumer redress to the Carbon Trust. These monies are to be used to help SMEs across Great Britain save energy via energy saving audits and advice, and installation of energy efficiency measures.
Furthermore, E.ON agreed to pay an additional £7 million if it did not achieve an installation target for its outstanding meter points by 2 November 2016.
E.ON achieved its installation target on 30 August 2016.
17 Dec 2015: Investigation into Economy Energy’s compliance with its obligations under the gas and electricity supply licences (Standard Licence Conditions 23, 24 and 25)
Type as published: Enforcement case. Published 17 Dec 2015. Closed 17 Dec 2015. Status as published: Closed.
Decision (as Ofgem words it): Notice of decision to impose a financial penalty on Economy Energy following our investigation into its compliance with its obligations under the gas and electricity supply licences (Standard Licence Conditions 23, 24 and 25)
The Authority has confirmed its decision to impose a financial penalty on Economy Energy following an investigation into its compliance with a number of relevant conditions set out in SLCs 23, 24 and 25.
We launched our investigation in response to a referral from Consumer Futures. The investigation considered whether Economy Energy complied with its licence conditions when marketing gas and electricity to its customers pre February 2014.
The provisions of SLC 23 and 25 govern the notification of domestic supply contract terms and the marketing of gas and electricity to domestic customers.
Under SLC 23.1, suppliers must take all reasonable steps to communicate the principal terms of their contract to the customer before they enter into it. Under SLC 23.3 and SLC 23.4, suppliers are required to give customers at least 30 days’ notice of a price rise allowing customers the chance to terminate the contract without incurring exit fees and switch before the increase takes effect.
Under SLC 25.1 and SLC 25.2, suppliers must ensure all information they give to customers in the course of their marketing activities and/or its telesales activities is:
complete and accurate and is capable of being easily understood; and
not misleading and fair in its content and how it is presented.
They should also ensure their representatives behave in a fair, transparent, appropriate and professional manner.
Under SLC 25.6, SLC 25.7 and SLC 25.8, suppliers must provide a written estimate of the total annual charges before entering into a contract with a customer in the course of their marketing activities. Where a comparison with another supplier is made, a best estimate of comparable charges should be provided with any differences explained clearly.
Under SLC 25.5, customers should be able to understand they have entered into a contract with a supplier. Therefore, suppliers must ensure their representatives readily identify themselves to customers. Suppliers must put in place and follow appropriate procedures for the selection and training of sales staff who are engaged in communicating with customers for the purposes of their marketing activities.
Under SLC 25.16, suppliers should take all reasonable steps to ensure the management arrangements they put in place help them comply with their licence obligations.
Economy Energy has admitted that it breached the SLCs listed above. The investigation also looked at whether Economy Energy incorrectly charged exit fees (SLC 24.3) and whether it provided written estimates to customers (SLC 25.9). There was no finding of breach in relation to these SLCs.
The Authority has confirmed its decision to impose a financial penalty of £1. This is in addition to £250,000 (less £1) that Economy Energy has paid to Citizens Advice. This redress payment will be used towards the Energy Best Deal Extra Prepayment Meter project, the aim of which is to provide advice and information to vulnerable consumers with prepayment meters. Economy Energy will also take further steps to trace and refund customers who lost out financially as a result of either being mis-sold contracts or not being advised of price increases. Economy Energy has also paid unclaimed monies to the National Children’s Bureau.
17 Dec 2015: Notice of decision to impose a financial penalty on E.ON following an investigation into its compliance with Standard Licence Condition 12 of the Electricity Supply Licence
Type as published: Enforcement case. Published 17 Dec 2015.
Decision for (as Ofgem words it): Investigation into E.ON’s compliance with its obligations under the electricity supply licence (Standard Licence Condition 12)
The Authority has confirmed its decision to impose a financial penalty on E.ON UK Plc and E.ON Energy Solutions Ltd (together referred to as "E.ON") following an investigation by Ofgem into its failure to comply with Standard Licence Condition 12 of the Electricity Supply Licence (SLC 12), in relation to advanced meters for non-domestic premises.
The Authority found that E.ON breached the SLCs listed above; E.ON admitted the breaches.
The Authority confirmed its decision to impose a financial penalty of £2. This in addition to £7 million (less £2) that E.ON agreed to pay in consumer redress to the Carbon Trust. These monies are to be used to help SMEs across Great Britain save energy via energy saving audits and advice, and installation of energy efficiency measures.
Furthermore, E.ON agreed to pay an additional £7 million if it did not achieve an installation target for its outstanding meter points by 2 November 2016.
E.ON achieved its installation target on 30 August 2016.
14 Dec 2015: Adret Ltd: Investigation into whether there has been a contravention of Rule 5.13.1(b) of the Capacity Market Rules
Type as published: Enforcement case. Published 14 Dec 2015. Closed 14 Dec 2015. Status as published: Closed.
Decision (as Ofgem words it): Notice of Decision into whether Adret Ltd (previously GFE 2017 Ltd) and Berangere Ltd (previously GFE 2015 Ltd) complied with the requirements of Rule 5.13.1(b) of the Capacity Market Rules
In May 2015, Ofgem opened an investigation into Adret Ltd’s compliance with Rule 5.13.1 (b) of the Capacity Market Rules.
In particular Ofgem investigated whether Adret Ltd provided false or misleading information to the Delivery Body regarding whether it had obtained all Relevant Planning Consents in relation to certain Capacity Market Units (CMUs) which participated in the T-4 capacity auction in December 2014.
The Authority has decided that Adret Ltd contravened relevant requirements (as defined in section 25(8) of the Electricity Act 1989), namely the requirements of Rule 5.13.1(b) of the Capacity Market Rules.
The Capacity Market is part of the Government’s reforms intended to ensure sufficient capacity on the system to provide a reliable electricity supply. National Grid run an annual auction to decide which generators and providers of demand side response will be awarded a capacity agreement, in return for providing capacity at times of system stress. Companies had to submit applications for the first of such auctions in November 2014 and National Grid awarded the contracts in January 2015.
The Authority has found that Adret Ltd submitted false and misleading information when applying to be part of the 2014 capacity auction, which is a Prohibited Activity under the Capacity Market Rules. As a result the Authority found Adret Ltd had contravened a relevant requirement set out in Rule 5.13.1(b) of the Capacity Market Rules in respect of one generating unit: G17JAM.
The Authority has considered all of the circumstances of the investigation and the Prohibited Activities undertaken by Adret Ltd and Berangere Ltd which belongs to the same group of companies as Adret Ltd and concluded that G17JAM was in breach of the Capacity Market Rules.
Adret Ltd has accepted the Authority’s findings and decision.
14 Dec 2015: Berangere Ltd: Investigation into whether there has been a contravention of Rule 5.13.1(b) of the Capacity Market Rules
Type as published: Enforcement case. Published 14 Dec 2015. Closed 14 Dec 2015. Status as published: Closed.
Decision (as Ofgem words it): Notice of Decision into whether Adret Ltd (previously GFE 2017 Ltd) and Berangere Ltd (previously GFE 2015 Ltd) complied with the requirements of Rule 5.13.1(b) of the Capacity Market Rules
In May 2015, Ofgem opened an investigation into Berangere Ltd’s compliance with Rule 5.13.1 (b) of the Capacity Market Rules.
In particular Ofgem investigated whether Berangere Ltd provided false or misleading information to the Delivery Body regarding whether it had obtained all Relevant Planning Consents in relation to certain Capacity Market Units (CMUs) which participated in the T-4 capacity auction in December 2014.
The Authority has decided that Berangere Ltd contravened relevant requirements (as defined in section 25(8) of the Electricity Act 1989), namely the requirements of Rule 5.13.1(b) of the Capacity Market Rules.
The Capacity Market is part of the Government’s reforms intended to ensure sufficient capacity on the system to provide a reliable electricity supply. National Grid run an annual auction to decide which generators and providers of demand side response will be awarded a capacity agreement, in return for providing capacity at times of system stress. Companies had to submit applications for the first of such auctions in November 2014 and National Grid awarded the contracts in January 2015.
The Authority has found that Berangere Ltd submitted false and misleading information when applying to be part of the 2014 capacity auction, which is a Prohibited Activity under the Capacity Market Rules. As a result the Authority found Berangere Ltd to have contravened a relevant requirement set out in Rule 5.13.1(b) of the Capacity Market Rules in respect of one generating unit:G15MAT.
The Authority has considered all of the circumstances of the investigation and the Prohibited Activities undertaken by Adret Ltd and Berangere Ltd, which belong to the same group of companies, and decided to issue a direction to the Delivery Body to terminate the capacity agreement awarded in relation to G15MAT. Additionally, G15MAT is disqualified from participating in capacity auctions taking place in the next two delivery years.
Berangere Ltd has accepted the Authority’s findings and decision.
12 Nov 2015: Alkane Energy UK Ltd: Investigation into whether there has been a contravention of Rule 5.13.1(b) of the Capacity Market Rules
Type as published: Enforcement case. Published 12 Nov 2015. Closed 26 Aug 2015. Status as published: Closed.
In May 2015, Ofgem opened an investigation into Alkane Energy UK Ltd’s compliance with Rule 5.13.1 (b) of the Capacity Market Rules.
In particular Ofgem investigated whether Alkane Energy UK Ltd provided false or misleading information to the Delivery Body regarding whether it had obtained all Relevant Planning Consents in relation to certain Capacity Market Units (CMU’s) which participated in the T-4 capacity Auction in December 2014.
We have decided to close the investigation as Alkane Energy UK Ltd has provided Ofgem with information which confirms that there was not a breach of 5.13.1 (b) the Capacity Market Rules.
Cases 151 to 165 of 252. Page 11 of 17. Every row is on one of these pages.
Contains public sector information licensed under the Open Government Licence v3.0.